How accountable can Contractors be held for scheduling errors? For example...
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 0
- 2
0
Project Had 1 day for install after long lead, then 1 day install, then Substantial Completion. But in fact the install and detail such as testing would take 30 days. The long lead is taking longer - they want more for "supply chain" disruptions (aren't thos over) - isn't all the delay on the contractor for under-estimating delivery, not getting procured in time, and the bad logic and or not enough duration. All on contractor to make up or get LD's?