How accountable can Contractors be held for scheduling errors? For example...

John ReevesMember for 13 years 5 months
Created
0
2
0

Project Had 1 day for install after long lead, then 1 day install, then Substantial Completion.  But in fact the install and detail such as testing would take 30 days.  The long lead is taking longer - they want more for "supply chain" disruptions (aren't thos over) - isn't all the delay on the contractor for under-estimating delivery, not getting procured in time, and the bad logic and or not enough duration.  All on contractor to make up or get LD's?