P6 WBS is Hierarchy is mismatching in activity Window

Rajkumar SMember for 14 years 11 months
Created
1
5
0

Hi, I required troubleshooting in my P6, The WBS Hierarchy sequence is not followed in my activity window in my P6. This started when I imported an external .exr file into my P6. My whole P6 has started to follow the WBS disturbance. The screenshots are enclosed. Anyone Welcome to provide a solution. Thank you

1 reply

Oldest first
  1. 0
    David Kelly ·

    You should always zero fill

    You should always zero fill in P6.

    For example, a WBS code should be DAM.3.4.01 not DAM.3.4.1

    Just overtyping the WBS code with the new zero filled values should sort it