Global Change does not apply on a selected WBS
In the Open Standard
Rox LraMember for 8 years 8 months
- Created
- 1
- 3
0
Hi All,
I am trying to make a global change where I would like to increase the duration on a certain WBS withing the project. I have applied the condition and parameters however it applies on all activities from the project, which I do no want.
Any ideas?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?