what if the baseline is found to be wrong?

John ReevesMember for 13 years 5 months
Created
4
3
0

what if the baseline is found to be wrong?  -  can you then claim that the project is behind or ahead when the baseline critical path has changed?

4 replies

Oldest first
  1. 0
    David Kelly ·

    Saying the baseline is

    Saying the baseline is 'wrong' is like saying the contract is 'wrong'

    Who accepted what?

     

     

  2. 0
    Nkoketseng Konopi ·

    You have made two different

    You have made two different statements. This first being "the baseline is wrong", and the 2nd being that the critical path has changed. Which of the two statements do wish to be considered when answering your question? 

    What do you mean by "Wrong baseline"?

    1. Have you assigned the incorrect baseline?

    2. Is the official baseline itself not credible?

  3. 0
    Joselito Santillan ·

    What do you mean baseline is

    What do you mean baseline is wrong? Do you mean that the sequence of works cannot be executed based on the actual technical/ site conditions? or forecasted variables that may contribute to the delay of the project is not applicable to the implementation of the project? There are many circumstances wherein the baseline may not be applicable for implementation so kindly elaborate what you mean.

  4. 0
    Joselito Santillan ·

    What do you mean baseline is

    What do you mean baseline is wrong? Do you mean that the sequence of works cannot be executed based on the actual technical/ site conditions? or forecasted variables that may contribute to the delay of the project is not applicable to the implementation of the project? There are many circumstances wherein the baseline may not be applicable for implementation so kindly elaborate what you mean.

Log in or join to reply