periodic ETC curve

bambang PangestuMember for 23 years 8 months
Created
4
2
0
Dear planners,

What should I do if I need P3 to prepare a periodic ETC, lets say for the next 3 months, 6 months, etc. as its periodic (not the complete) early warning system.

thx

4 replies

Oldest first
  1. 0
    Ali Vessali ·
    Hi bambang,

    Actually I couldnt understand what you mean! Would you please explain more about your question?

    Regards,
    Ali Vessali
  2. 0
    Ed van der Tak ·
    Hi,

    Do you mean a filtered ETC on activities whitin the coming 3 months (a period)?

    Regards,

    Ed van der Tak
    ARAM Planning Consultants
    The Netherlands
  3. 0
    Anita Hunter ·
    I presume you are talking about a look ahead for the next 3 months / 6 months etc.

    If so all you do is run a filter asking for early dates within range of dd+0 to dd+12w or dd+24w what ever your look ahead is.

    Hope this is of help.
  4. 0
    Jorge Taguinod ·
    ETC curve?

    Are you referring to being warned about possible funding requirements every quarter (3 months, 6 months, 9, 12...)?

    Or are you referring to resource quantity information needed per quarter?

    Please clarify

    Jorge