S Curve - P3

J Venkatesh PMP PSP ACIArbMember for 20 years 2 months
Created
13
1
0
Frnds,

I have completed a schedule without any cost / resource loading..

Now I want to see what would be the monthly progress % ( S Curve) of the project...

I find difficult to see this without cost / resource loading...

Is there anyway to find the S Curve..

cany anyone help me in this...

J

13 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    Jaya,

    Define a resource named R.

    Run Global change and add R to all activities.

    Then run a global change Resource R = OD.

    You can now get the desired S-Curves which will be based on OD.

    Regards,

    Ashraf
  2. 0
    J Venkatesh PMP PSP ACIArb ·
    Dear Ashraf,

    Thanks for ur reply....

    T s not clear,,,am not convinced....can u explain this or is there any other way available...

    J
  3. 0
    Bijaya Bajracharya ·
    S curve for what? Usually you will use it for resource (number or cost), or cost. If you don’t have those parameters in the programme and you still wish to see S curve, you need to think of something - and original duration as suggested by Ashraf is a very good idea. Just think of Original duration as a resource.

    You can make an even simpler S curve. If you give your activty 1 point for starting and 1 point for finishing, you have two points each planned for every activity. In a number of occasions, even such an S curve comes as a very good project control tool. Now to get this curve in P3, you, of course need to create a resource S. You can then globally assign 2 units of it to all the activities.
  4. 0
    J Venkatesh PMP PSP ACIArb ·
    oops...I did it....

    Ashraf and Bijaya....Thank u...Thank u very much

    It worked well...

    J
  5. 0
    J Venkatesh PMP PSP ACIArb ·
    In MSP, to find the same..I will auto update the project keeping the data date as project end date considering all the activities are happened as well as planned..

    After this, I can take the S - curve / Monthly progress happened from the Reports and will plot the S-Curve...But any option, like that wud available in P3

    J
  6. 0
    Pranab Kumar Deb ·
    hello ashraf but i am unable to assign this resource r to all activities
    regards
    deb
  7. 0
    Ashraf Jahangeer ·
    Define the following Global Change.


    1. Add Resource
    If OD > 0 the Resourse = R

    2. Modify Resurce

    If OD > 0 then RDUR = OD


    First run 1 and then run 2.

    Regards,

    Ashraf



  8. 0
    Pranab Kumar Deb ·
    hello ashraf i have done exactly as per your advice still it is not working , when i run 1 , it say no activities affected
    regards
    deb
  9. 0
    Ashraf Jahangeer ·
    Try this Deb,

    1. Add Resource
    If OD > 0 the RES AD R

    Regards,

    Ashraf
  10. 0
    Ahmed Syed ·
    Hi Parnab
    Just a little change in Ashraf’s syntax
    Resouce +(ADD) R
    rather EQ
  11. 0
    Ahmed Syed ·
    Thanks Ashraf for your valuable tip.
    Infact, I also encountered the same problem as Parnab. But, then I changed the syntax with ADD and it worked fine.
    Cheers
  12. 0
    Pranab Kumar Deb ·
    DEAR ASHRAF AND AHMED,
    THANK YOU BOTH FOR THE HELP
    REGARDS
    DEB
  13. 0
    Ulysses Garcia ·
    Hi jaya,

    You made mention you have already allocated resoucres and cost to your schedule. to find s- curve more easy in tracking your progress, all you have to do firstly is to create a baseline to compare it to your current schedule which is data date. then in primavera p3 in tool menu,graphic, click resource & cost .if you want to see the overall cost or resource curve you may just type the command string as ?????? to the selection. However in Primavera P5 you may treat it in a dirrent way but basically homologous in nature. just go to Click menu Project, Tracking layout, resource usage then activity profile option, and set up your printing preferences to view your s-curve.

    Uly

Log in or join to reply