Dear P3 users;

I want to create a list of driven predecessors only. As you know in Predecessor field, P3 will list all Predecessors of each activity sorted by Act. ID, but I’m looking for a way to list just driven ones or at least show driven ones first then non-driven.
Anybody has experience or tips?

Thanks,
Ali Vessali

10 replies

Oldest first
  1. 0
    Khalid Abdelaal ·
    Dear Ali Alsalamo Alikom

    you can creat this list in tabular report (Tools-tabular report- Schedule)and from content window chose detailed predecessor.
    this report contains all predeccesor and signifies driving relation by astric *


    rega

    Khalid Abdelaal
  2. 0
    Ali Vessali ·
    Thanx Khalid,

    But you know the result of that report. Actually Im working on a detailed schedule with more than 5,000 activities. In such schedule there are several predecessors and/or successors for more activities. So, I want to create a report to show just Driven links to trace the logic easier.
    Any other suggestions?

    Thanks,
    Ali Vessali
  3. 0
    Forum Guest ·
    Dear Ali


    There is an excel file contains macro, you can get predeccessor through this file contains predeccessor and column contains driving relation if it drifing (True) or if it is not driving (false) so you can make a filter in Excel to delete (False) and you will find only driving relationship send me your email to send you the file

    my email
    kh_abdelaal@hotmail.com


    Khalid Abdelaal
  4. 0
    Nihat Yildirim ·
    Trace Logic might be configured so that it just displays driving activities. This is helpful.
  5. 0
    Ali Vessali ·
    Khalid;
    I think you are talking about RA application. But, anyhow would you please send your file to this address: avessali@yahoo.com

    Thanks,
    Ali Vessali
  6. 0
    Ali Vessali ·
    Nihat;

    Thanks, I will try that way.

    Ali Vessali
  7. 0
    Nishikant Choudhary ·
    Khalid , can u please share the excel macro with me , cos i think thats the best way , even i would like to test my relationships and logic in @ 4000 activities that i have to go through to ensure its veracity,please.


    Thanks and best regards,
    Nishikant
  8. 0
    Puneet Arora ·
    Khaled, you can save a lot of planners of misery. Can U mail the file to me please.

    Puneet
    puneet.arora@eil.co.in
  9. 0
    Syed Ali Hasan ·
    Hi,

    Most of the EXCEL file macros are supplied by Primavera Systems, Inc in the P3 3.0, P3 3.1 in the SUPPORT/UTILS/EXCEL folder in the CD. There are also other useful utilities in the Support folder of the CD. You can also download the latest EXCEL macros from Primaveras Knowledgebase on Primaveras web site.

    Best wishes,

    Syed Hasan
    Primaveras PAR in the Middle East.
  10. 0
    Jorge Taguinod ·
    Hi Ali!

    Based on your post, I agree with Nihats solution. If this is not acceptable to you, can you please explain why you need to get this so I can understand and perhaps provide another option.

    Best regards,

    Jorge P3 Taguinod
    Crown Systems

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?