Hi everybody.

I have the following question...how can i througth a global change make a update to all activities and change the drive resource selection to nothing...o else...pass the value active the selection of the option drive to not select?...

I hope that my question was clear.

Thanks to everyone for the help that you can give me...

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello,
    you can create the following global change:
    IF Activiy ID EQ "this & that"
    THEN RDRV (meaning Driving Resource Flag" EQ " " (just one space between quotes)
    Alexandre