Calendar
In the Open Standard
Nishikant ChoudharyMember for 23 years 11 months
- Created
- 5
- 1
0
How can i create a DOuble shift i.e. 2 X 10 hrs shift calendar and its benefit in terms of duration to be reflected in my schedule.
One way i think is to physically calculate the Units per time period for single shift and then multiply by a factor of 2 ,and then input in the resource table, so that the reflection is very close .
am i right in doing this ???? or is there a simlified way of doing it?
One way i think is to physically calculate the Units per time period for single shift and then multiply by a factor of 2 ,and then input in the resource table, so that the reflection is very close .
am i right in doing this ???? or is there a simlified way of doing it?
5 replies
Oldest firstLog in or join to reply