Calendar problem detected, Your project is too lon
In the Open Standard
Scott AitkenMember for 22 years 2 months
- Created
- 8
- 3
0
I’m getting the above message on Primavera Look when scheduling.
I think this is the error that is stopping me from extending an existing plan past a certain date (the dates are greyed out on the drop box, so I can’t move EF dates past a certain date).
I’ve made sure that the Project Overview Project must finish by is at the date I want, but the EF is at an earlier date.
I also took all start conatraint dates off that were before the data date.
Any ideas?
I think this is the error that is stopping me from extending an existing plan past a certain date (the dates are greyed out on the drop box, so I can’t move EF dates past a certain date).
I’ve made sure that the Project Overview Project must finish by is at the date I want, but the EF is at an earlier date.
I also took all start conatraint dates off that were before the data date.
Any ideas?
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?