P3 planned progress for specific cut off date

Anil GodhawaleMember for 23 years 4 months
Created
16
4
0
Hi friends,

I want to calculate the plan % complete progress for a specific cut off date. Say i would like to see the planned % progress as of 14 every month for the entire duarion of the project..Does P3 allows us to do so?

Please let me know if you didnt get my question..

Regards,

16 replies

Oldest first
  1. 0
    Forum Guest ·
    You could take a copy of the programme and then use tools - Update Progress. Use Excel to record the % complete for the schedule date and then keep repeat for the next date and so on.

    A bit of a ball ache but it works.
  2. 0
    Gilbert Rayco ·
    Anil,

    From ur base schedule, steps as follows:
    - tools,tabular reports,Resource,Loading
    - choose period u prefer(i.e. daily,weekly,etc)
    - modify, format, choose export CSV
    this will give the loading for period u prefer.

    Hope this can assist u.

    Gilbert
    2598
  3. 0
    Forum Guest ·
    Thanks,

    Well, there is a bit of problem in doing so..Say you gives it weekly ..P3 takes a week ending date..It is not necessary that this date will be 14th for every month..I agree we need to pick nearest possible date to 14th..My requirement is i should get the Plan progress exactly as of 14th every month..See if there is any way of doign so...

    Regards,
  4. 0
    Anil Godhawale ·
    Thanks,

    Well, there is a bit of problem in doing so..Say you gives it weekly ..P3 takes a week ending date..It is not necessary that this date will be 14th for every month..I agree we need to pick nearest possible date to 14th..My requirement is i should get the Plan progress exactly as of 14th every month..
    If we tailor the report for daily..you would agree that it will be a huge one and calculating from that would be difficult thought not impossible..

    See if there is any way of doign so...


    Regards,
  5. 0
    Mk Tse ·
    If the specified cut-off date is same as data date, make the life easy?
  6. 0
    Anil Godhawale ·
    Well i requiremnent is to calculate the planned % complete for the entire duraiton of project during the begineinig stage or from the Target schedule..

    Data date feature is useful only when the project is running or when it becomes the current schedule..


    Regards,
  7. 0
    Mk Tse ·
    Fill the % in a custom data field by formula in global change. eg OD/project duration.
  8. 0
    Zq qz ·
    To do this just make new target1 or target 2. and using Update progress option you can estimate or determine progress at any given time or date. Try this hope this will help
    MMD
  9. 0
    Jorge Taguinod ·
    Hi Anil,

    Id recommend that you run >Tools >Tabular Reports >Cost >Loading.

    Modify CL-01:
    >Resource Selection = Blank
    >Selection = Blank
    >Timescale = Project Start Date (SD) to Finish Date (FD)
    = Unit=Daily
    >Format = Export Report in CSV; Organize by Cost Account

    This report will create a daily spending plan.

    In Excel, you can create sums (range is from 15th of previous month, to 14th of current month, and 15th of current month to 14th of next month... an so on.)

    In Excel, divide each sum by the total project cost and multiply by 100. This should give you the percentages you need.

    Hope this works.

    Jorge

  10. 0
    Forum Guest ·
    Hi Anil,

    This question was answered earlier by one of our members.

    In short, please take your target plan and name it T2.Go to Tools and update progress to the datadate you require. Now while updating your update file,use T2 file as target2.Now in the update file call for the column " Target 2 % progress"

    Hope this clarifies your doubt. If you need further assistance please call me on 050-6346395.

    Regards,

    Tara Muddappa
  11. 0
    Tara Muddappa ·
    hi Anil,
    Sorry i had posted without logging in.

    Tara muddappa
  12. 0
    Kader Oli ·
    HI ANIL,

    IF YOU UNDERSTAND MR.GILBERTS IDEA, YOU COULD HAVE SOLVED UR PROBLEM. THIS IS THE ONE SIMPLEST WAY FOLLOW HIM

    - choose period u prefer(i.e. daily,weekly,etc)

    AND MAKE IT AS DAILY (DESPITE WEEK OR MONTH) AND EXPORT IT TO CSV.

    THEN ITS EASY TO YOU TO FIND CUMULATIVE DAY BY DAY USING EXCEL FORMULA. AND THEN U CAN CALCULATE WHATEVA U WANT EITHER 14TH OR 17TH OR ANY DATE U NEED.

    BELIEVE THIS IS THE ONE SIMPLEST METHOD WE CAN DO WHAT YOU NEED.

    THANKS & REGARDS

    PE



    Anil,

    From ur base schedule, steps as follows:
    - tools,tabular reports,Resource,Loading
    - choose period u prefer(i.e. daily,weekly,etc)
    - modify, format, choose export CSV
    this will give the loading for period u prefer.

    Hope this can assist u.

    Gilbert
    2598
  13. 0
    Anil Godhawale ·
    Hi all,

    Thanks for the comments. Well, the solution by resource loading report with daily format is quite exhaustive. As in this you need to export data in excel and work out accordingly. I was looking for some direct way of calculating the progress like we does it for monthly basis.

    The other option some of you guys have given is to update the progress by keeping the same data date in target say T1 or T2. This doesnt help as my intention is to calculate the % for entire duration of the project with cut off being specific date of the month. If we use update progress option in say Target 1, it may give the right % for the 1st month, however when we tries to measure % for the 2nd month, it will shift the entire project by one month as the project is not updated. Also one need to perform this function for 36 times if the prject duration is 3 years, which i would like to avoid.

    Anyway, i wrote this issue to P3 guys and they also dont see any other option than we discussed above so i have a very little hope of sorting this out as per my requirement.

    Once again thanks to all of you for such a active participation.

    Best Regards,

    Anil Godhawale,
  14. 0
    Tara Muddappa ·
    Hi Anil,

    To arrive at the planned percentage for the whole project, then the other solution is please do as follows:

    1.0 By using global change add a Resource "Progressindex"
    2.0 Make OD=BQ of the above said duration.(Through global change)
    3.0 Through Graphical reports generate a graph and you end up having ES curve and LF curve shown as % progress.

    Hope this will be of help,if you need further assistance please call on me.

    Regards,

    Tara Muddappa
  15. 0
    Anil Godhawale ·
    Hi Tara,

    I tried to do accordinlgy however no success. Can you please elaborate coz i may be understading it wrongly..

    Thanks

    Anil Godhawale
  16. 0
    Jorge Taguinod ·
    Hi Anil,

    I think Tara was referring to my answer in one of my prior posts. Can you browse the previous posts and search for my answer? Hope you find it because I did post a detailed answer.

    Jorge