How to get % Planned for the baseline ?

Sandip ChakrabortyMember for 20 years
Created
15
3
0
Hi,

Need a help.....

Wanted to know.... how can we get the % Planned for the baseline prog at any given data date .....

Regards

Sandip

15 replies

Oldest first
  1. 0
    Karim Mounir ·
    Sandip,

    It depends on the method that u will use to measure the actual progress % (eg. u will measure the actual progress in the same way u will measure the planned progress of the baseline).

    Regards.
  2. 0
    Sandip Chakraborty ·
    Hi Karim,

    What i was asking was can P3 generate on its own the % Planned for each activity as per the baseline schedule ? Like MSP can do ?

    Actual progress i will feed manually .....Hope am able to make my question clear to you ....

    Regards

    Sandip
  3. 0
    Karim Mounir ·
    Sandip,

    actually i don’t know about the % planned which is automatically generated in MSP.

    What i meant is that u have to monitor the actual progress in the same way u have planned for.

    eg. if u want to monitor progress based on "Units of measure" then u have to load your baseline & updated schedule with the same "Units of measure".
    Then after u completed your baseline u make for example S-Curve or a report for some activities having same "Units of measure" which will give u the planned % at a certian data date.
  4. 0
    David Kelly ·
    Gosh, thought everybody knew how to do this.

    Take a copy of your project with no progress, a copy of the original baseline will do.

    Then progress that project using the "update progtress" facility to the current data date. That means that every activity in the project will have a percent complete as if the project had been executed exactly as the baseline proposed.

    Now make that project a Target, e.g. Target 2, of the current plan.

    The field "Target 2 percent complete" is Planned percent complete.

  5. 0
    Sandip Chakraborty ·
    Thanks a lot David...Got it now....
  6. 0
    Mohammed Foudeh ·
    Dear all :

    to get the accurate Planned % you have your schedule loaded with manhrs..then go to tools/reports/resources/tabular ..and choose all the resources,export this file to excel,then find your planned percentage by dividing the early usage(Cumm.) by the total man hrs then multiply by 100 %,you will get your planned percentage accurately based on physical progress,,also you can find the planned % for late schedule in the same way.

  7. 0
    Althaf Mohamed ·
    How do i calculate planned % of an activity (Based on what). is it Quantum of work ,Manhours, Cost or Duration.
  8. 0
    Althaf Mohamed ·
    hi All,


    Can anybody tell me What ACWS means Actual Cost of Work Scheduled.


    PLZ do let me know if there is any thing like ACWS
  9. 0
    Mimoune Djouallah ·
    Review earned value

    The Budget Summary form displays the planned value (BCWS) and earned value (BCWP). In earned value analysis, you can compare BCWP to the BCWS and to
    the actual to date (ACWP).
    The planned value reflects the work that should have been finished as of the data date according to the target plan; earned value measures the value of the work
    actually accomplished as of the data date. The difference between these two figures is called schedule variance (favorable if the earned value exceeds the
    planned value). The difference between ACWP and earned value is called cost variance (favorable if the earned value exceeds the actual cost).

    copy past from P3 help ;)

    regards
    mimoune
  10. 0
    Zq qz ·
    If your schedule is resource loaded.

    say cost: review your EVMS. Also you can generate in your resouce loading using cost.(use your baseline to generate this)

    if using Manhours/mandays and its loaded in the BQ. lso you can generate in your resouce loading using resource.
  11. 0
    Francois Holtzhausen ·

    Good day   Do any one have a

    Good day

     

    Do any one have a formula for plan%

    thank you

  12. 0
    Bong Yagahon ·

    Gentlmen, Its very simple.

     

    Gentlmen,

    Its very simple. Here's how to generate % planned for each activity.

      There are two schedules that you are actually managing in any given project who uses P3. First is the Baseline Schedule also known as theTarget schedule and the second is the Actual Schedule also known as the Current Schedule. In other words, your target/baseline schedule is your PLAN and the current schedule is your ACTUAL and FORECAST schedule. BEfore the DATA DATE your Actual Schedule  and after the DATA DATE your forecast schedule So, below are the steps, just follow the following:

                1. Close the current schedule and open the target schedule by clicking file, open and then click the file name of the target schedule in the file opening dialogue box.

                2. Once the file opens, click Tools> update progress and enter the data date, Then choose all activities and click UPDATE.

                3. After the progress was updated, click format column tool bar, and add a column named Percent Complete.

                4. On this column the percent complete of every activity will appear. Since this is you target SCHEDULE or YOUR PLAN SCHEDULE, every percent COMPLETE therefore that appear on every activity is the % plan of every activity on this DATA DATE.

    Hope this help. GOod Luck.

     

    Pio

      

  13. 0
    john Cohello ·

    It stands for Actual cost of

    It stands for Actual cost of work scheduled.Its self explanatory .

  14. 0
    Safak Vural ·

    Dear planners,If you are not

     

    Dear planners,

    If you are not using resource curves, fancy calendars and your activity durations are not high, then you can use a custom data item and global changes formula below to have an approximate planned % for activity for schedule layouts.

    Custom Data Item: PL%

    GC1

    PL% = (DD – PLST) / (PLFN – PLST)*100

    GC2

    If PL% < 0 then PL% = 0

    GC3

    If PL% > 100 hen PL% = 100

    Assign a letter (“P” maybe) in tools-tabular reports-production

    Assign PL% to a column in your layout. After every update run report series “P” and reorganize your layout.

    I recommend having a second target and updating it manually which is much more accurate (This method neglects resource profile distortion due to calendars) but this is a quick solution. This algorithm can be also used in report writer and other stuff to have planned % for an activity for a specific data date.

    Regards,

    Safak

     

  15. 0
    Bong Yagahon ·

    <

    <