As Late As Possible Scheduling

Ugo MarsolaisMember for 23 years
Created
3
1
0
Is there anyway to force P3 to systematically schedule ALAP (as late as possible) without having to use constraints on every task?

For now, I have only been able to do this by forcing the Zero free float constraint on each task. This then forces all tasks to start as late as possible.

The reason why I am doing this is for a pilot project on using Critical Chain in P3. And Critical Chain requires that you schedule ALAP instead of the traditional ASAP.

3 replies

Oldest first
  1. 0
    Alphons Bruns ·
    Hello Ugo,

    In Bars you can select the late bar to show instead of the early bar. just go to bars and select the late bar to make it visible.

    Regards Alphons
  2. 0
    Ugo Marsolais ·
    Thanks Alphons for the answer. I did not thought about that since I believed this was only a display trick...

    But by trying it I have realized that since P3 is calculating a late start and finish date, this basically means P3 is scheduling ASAP and ALAP simultaneously, is that right?
  3. 0
    Alphons Bruns ·
    That is correct Ugo because it calculates on a forwart pass and also on a backward pass. So the late schedule indeed shows a as late as possible schedule.