scheduling an activity
In the Open Standard
Maria Joane PagunuranMember for 22 years 5 months
- Created
- 11
- 3
0
Hi to all,
I’d like to know how to divide the duration of an activity without dividing this activity into sub-activities.
Say for example:
Activity A has to be finished in 12 months’ time. Say, January - December. But due to the anticipated negative weather conditions from June to August, we are planning to stop operations on these months.
My question is: how can I schedule this activity showing its duration from January to May, stop work from June to August, then continue/finish the activity from September to March? Thereby retaining the 12 months duration, without dividing Activity A into Activity A.1,A.2 & A.3.
Hope somebody out there could enlighten with this.
Thank you very much.
Joane
I’d like to know how to divide the duration of an activity without dividing this activity into sub-activities.
Say for example:
Activity A has to be finished in 12 months’ time. Say, January - December. But due to the anticipated negative weather conditions from June to August, we are planning to stop operations on these months.
My question is: how can I schedule this activity showing its duration from January to May, stop work from June to August, then continue/finish the activity from September to March? Thereby retaining the 12 months duration, without dividing Activity A into Activity A.1,A.2 & A.3.
Hope somebody out there could enlighten with this.
Thank you very much.
Joane
11 replies
Oldest firstLog in or join to reply