Resource Allocation
In the Open Standard
AG
Anil GuptaMember for 23 years 2 months
- Created
- 23
- 5
0
Hi All
Would You please let me know whats the fastest way of allocating multiple resources to activities.I tried using Global change...There also i had follow two or three cycles for allocatiion..
I would appreciate the early and elaborate answers..
Thnx in advance
Anil
Would You please let me know whats the fastest way of allocating multiple resources to activities.I tried using Global change...There also i had follow two or three cycles for allocatiion..
I would appreciate the early and elaborate answers..
Thnx in advance
Anil
23 replies
Oldest first- 0AGAnil Gupta ·Thnx gentlemen for your advice,I tried export/import function also.
But incase of Mutliple resources in one activity.It is still a cumbersome method. Comma sintex does n’t work...i have to create separate row with different resouce for allocation..E.g if i have to allocate resource A & B to activity 1 then just by putting A,B in resource Id column, it doesn’t work.It can be done only by creating a separate row for activty id 1 and then allocating both resources separetly in two cells accordingly.
In that case i think global change is still faster method.
Please comment if i am wrong in export / import method or if there is anyother way.
Regards
Anil - 0MTMk Tse ·Yes, you right. One row for one resource only on spreadsheet.
My practice is each import by Excel is only for one resource. After import, then in Excel find and replace the resource from A to B, save and for another import.
I prefer this methodology for easy control. Each time only one resource import, if any go wrong, easy to trace. - 0BVBhuvaneswaran Velayudhem ·Ok,I think you misunderstood, I told to insert as many similar lines in X-L using macros and u can add the additional recourses automatically in a single import.
Yes, I accept that the step mentioned by importing two or three times will also help. Which ever easier and most familiar we can use.
Regds.,
- 0AHAli Hamouda ·hi Anil.
I am applying the following way :
repeat the activity ID and assign different resources as much as you repeat the ID of the activity in Excel sheet.
ex.
ID Resource
z100h Plumber
z100h welder
z100h helper
and so on for any number of resources
this is similar to import 3 times.but if you repeat the activiy 3 times you will import 1 time
- 0MTMk Tse ·To solve one time import only, we need listed add input line on the speadsheet.
Most situation, we fail on the additional lines due to the range of import on shhet is not specified or revised.
e.g. if we export for 10 lines as template, then we change those value and add 10 more lines. Only first 10 lines are import successfully and the new 10 is ignored. It is due to the specified range still lock to the original records. - 0PAPodolny Andrew ·Hi, guys.
Why don’t you use P3 extensions. See installation diskSupportUtils. There are a lot of utilities in Excel format (see subdir Excel). For resources allocation use ACTIVITY.XLS or ActivityMod.XLS programs (be sure that u have Security level set to Medium in Excel) otherwise the macros won’t work. Check the main worksheet - it’s self-explanatory. Good luck! - 0MMMohammed Muneeruddin ·hi friends,
I switched to CCS for being user friendly in resources allocating and cost control. The main thing is that we speak the same language what we did for preparing the estimate.
Further during the pre-bid stage we use the cashflow module for predicting the amount and timing of maximum funding required.
Regards,
muneer