resource puzzel
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 18
- 5
0
our client has requested a program in p3 in days.
we work a 46hr (5 day) week. 8hr standard, 2 hrOT Mon-Thur and 6hrs on Fri.
i’ve allocated resource to the monday to thursday work and seperatly for the friday. i allocated a 4 day resource calendar for the M-T with fridays off and 1 day for the friday.
However when i add 1 unit to the resources of a 5 day activity it allocates 5 units of work to each and charges accordingly, i need 4 and 1. there not driving.
dose anyone know what i am doing wrong?
we work a 46hr (5 day) week. 8hr standard, 2 hrOT Mon-Thur and 6hrs on Fri.
i’ve allocated resource to the monday to thursday work and seperatly for the friday. i allocated a 4 day resource calendar for the M-T with fridays off and 1 day for the friday.
However when i add 1 unit to the resources of a 5 day activity it allocates 5 units of work to each and charges accordingly, i need 4 and 1. there not driving.
dose anyone know what i am doing wrong?
18 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?