Revised Target CPM
In the Open Standard
Mirza Gulam Hussain MazindraniMember for 24 years 6 months
- Created
- 3
- 1
0
The contractor’s CPM for a project consists about 3000 activities and upon studying, the Client requested the contractor to amend some activities(say around 25 activities).
The question is, how to know that the contractor has amended only the said 25 activities and did not make any changes to the other 2975 or so activities.
The question is, how to know that the contractor has amended only the said 25 activities and did not make any changes to the other 2975 or so activities.
3 replies
Oldest firstLog in or join to reply