Regarding Target file
In the Open Standard
SK
Sunil KumarMember for 21 years
- Created
- 25
- 5
0
I have a query regarding target and current schedule.... I had created a target file before updating......
If i want to do any changes.. for example i want to add extra duration for a particular resources of a activity then i have to do it in my cuurent schedule or target file.. where i have to do changes???
If i want to do any changes.. for example i want to add extra duration for a particular resources of a activity then i have to do it in my cuurent schedule or target file.. where i have to do changes???
25 replies
Oldest first- 0SSSukumaran Subaramaniyan ·Sunil,
Have you submitted the baseline schedule to your consultant.
a) If Yes! Then your updated target schedule become your Revised Baseline Schedule. Submit to consultant for approval.
b) If No! Update the target schedule and submit as a Baseline Schedule to consultant for approval.
Regards. - 0CAChristian Adrian De Vera ·Sunil,
There’s no need for you to update your target file (Baseline of your current file) coz that’s the original plan from the time you have submitted it to your client (if have submitted and accepted by your client), if you have to make some changes then do it in your current file (just like what Zhang said..),as this should reflect all the progress of your project..
Just to add some thought..
Regards,
Christian
- 0GBGordon Blair ·Sunil,
I agree wholeheartedly with the above.
Just one more thing to offer:
It may be that at some time the change to the plan is so significant that the client wants a new baseline to measure the Plan against (... am waiting for Clive and Oscar to wake up and shout at me...). In this case, make a copy of your first Baseline, assign that Copy as Target1 (with a new title e.g. Revised Baseline..) and update changes on Baseline through your working programme.
Note: This exercise is really only for when Snr Mgmt or the Client request a Change to the measurement Baseline. You must still maintain the original Baseline for Reference or in the event of Claims etc. - 0SMSen Moc ·That’s why in P3 you are given the chance to create two (2) Targets.
Target 1 – you can store the original baseline schedule (as per contract).
Target 2 – you can store the revised baseline schedule or your calculated schedule during the previous updating period.
And there’s another way to add Target 3, if Target 1 & 2 were already utilized, by using Custom Data Items.
Regards,
Sen
- 0SMSen Moc ·Sunil,
Here’s a direct answer on your post No.3:
I mean once i created a target file( baseline of current schedule) whatever i do i have to do it in currrent schedule ?? Am i right????
Yes, you are correct.
In P3, the current schedule is kinda your working file. Changes, progress updates, revisions, etc – you do it in Current Schedule.
If i had to update my target file i have to do it from update command????Am i correct...
Yes, you’re correct again BUT “be cautious in choosing the update options” (Tool/Project Utilities/[Select Target]/Update) – if you’re not careful, there’s a possibility that your Target schedule might be made equal to the Current Schedule (unless you’re progress is on schedule). In this case always keep a back-up copy of your target file before updating it.
Another way, and it’s the safer way, is to open the Target file separately. Make a copy or back-up file. Then, do the updations on the copied Target file. Once the copied Target is finalized and updated, you can now replace the existing Target of your current schedule by the Updated Target.
Again, a reminder: DO NOT UPDATE TARGET (or Baseline Schedule) UNLESS NECESSARY.
Regards,
Sen
- 0SKSunil Kumar ·Sen
That was a nice explaination.. thanx alot....
i had a query regarding tracking
1. If my resources exceeds than what i planned ( consider the type of activity is task) then i have to change it in resouces or not... coz my budget is going to increases...
where i have to do changes???
- 0SMSen Moc ·Sunil,
If your resources is more than Planned, you can either increase the Resource or the Duration. In either case, you will be OVER BUDGET (accept this!) because your planned budget is not enough or the planned productivity is high and your actual productivity is low.
If budget is your concern is Budget, you should have a higher productivity than planned. That is, pressure the men and make the equipments do more work at site. This however will be the PM’s job, not yours.
Regards,
Sen
- 0SMSen Moc ·Ok, Edgar. The subject will now shift a bit…
Performance can be measured and monitored in two ways: by SPI (Schedule Performance Index) and by CPI (Cost Performance Index), also known as Earned Value Management or EVM. In SPI you compare Planned Schedule vs. Actual; while in CPI you compare Planned Cost (or Resources) vs. Actual.
- 0DSDinishwar Singh ·hello christian
not getting to open the project at all..
message "Target project not found"
this is standard with p3, however i tought there was a way to get around this.
meaning , if there is a folder with all the current project p3 files and the target p3 files , if the target files for that project were deleted and an attempt to open the current project files gives the above error "Target project not found" - 0DGDaison Garvasis Pekkattil ·I guess this thing cant be generalised. It depends on the scenario.
1) If the changes are addition in scope, it could be worthwhile to come to an agreement with client and incorporate the additional scope.
2) If the changes are to the durations and relations of the existing activities it depends on how you want to go about it. Either you leave your baseline as it is and change the current project only in which case you are not comparing apple to apple.
or you discuss and decide to revise the baseline so that when you are tracking the progress, there is difference in the durations and relationships in target and current project.
One has to really see what suits your project.