P3 to P3e transfer

Chris StonesMember for 22 years 7 months
Created
3
2
0
My client has recently upgraded to using P3e and now cannot seem to open the monthly P3 progress we send.

As I have not experienced P3e, is there a way of sending the P3 data in a format that P3e will understand?

One thought we did have was that it may be the difference between the server type that is casuing the problem??

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    Owners of P3e can import and convert P3 schedules into P3e schedules. Have them open P3e and then select File / Import. The rest of the steps are explained in the manual and in the help file. (For the record, P3 cannot import P3e schedules. You have to ask the P3e Owner to export to P3 first.) Good luck!

    Ron Winter.
  2. 0
    Mk Tse ·
    Chris, may I know what error message or incorrect result you client have?
  3. 0
    Mk Tse ·
    By elimiation, would you mind do some tests: -
    - Export P3e/c to P3 and then import the output back to P3e/c without modification. (To identify and problem on P3e/c import/export function)
    - Export to P3, open P3, any problem (Check is export file is OK)
    - Export to P3, open P3, close without modification, import to P3e/c (check P3 software is problem source)
    - Export to P3, open P3, close with modification, import to P3e/c (check P3 software is problem source)

    The above test are on two machines, one P3e/c, one P3. Check the finding. Then cross machines.

Log in or join to reply