Checking of Programme

Forum GuestMember for 17 years 8 months
Created
7
4
0
For the huge project that consist more than 10,000 activities, how to check the relationship and data on each activities everytime the contractor submit the weekly updated programme? I mean to check are they really manipulate the programme in order to make good in the progress.

7 replies

Oldest first
  1. 0
    Luca Basile ·
    Did You try with Dig claimer?
    It look like is working with P3 but has some problems with P3e.

    If You go in Winter web page has also produced some schedule analyzer (also working with P3e) that may help you.
  2. 0
    Mk Tse ·
    Claim Digger only spot the difference between projects. If you want to check any manipulation for progress, refer to export P3 data into database. Define your checking rules into steps and validate the data.
  3. 0
    Forum Guest ·
    Dear mktse,
    Can you kindly explain in detail how to export P3 data into database, define the checking rules into steps and validate the data? Million thanks to you.
  4. 0
    Raj Singh ·
    The most painful part is preparation of the program for the first time. Once it has been agreed by all the parties you should obtain the soft copy.

    As I understand your primary concern is Manipulation by the Contractor. Well! I will breakdown your concerns into following areas:

    Activity Data : Especially Original duration
    Lags Data : Pred, Succ connections, type of lag, duration
    Progress Data : Activity, Progress %, Rem Durn etc.


    Without resorting to any fancy software export the data in similar way all the time to excel.

    Arrange the columns in similar way such as sorted on Pred, Succ

    Bring the update data in similar way and post it in the same sheet

    subtract the doubtful columns to find the change


    If there is any modification you will be able to see it in no time at all

  5. 0
    Forum Guest ·
    Dear all replied planner, I would like to enquiry if any software or programme to check the diferrent instead of export to Ms excel to compare manually?
  6. 0
    Ronald Winter ·
    If you are using P3, for checking only one schedule (the Baseline Schedule) there is only one software; SA Pro.

    For checking two P3 schedules to see the difference, there are three software packages,

    SA Pro

    Claim Digger (now surprisingly sold by Primavera in completion with their other ‘approved’ partners.)

    Primaplan Investigator

    If you are using P3e or P3e/c, then the choices is Claim Digger (built-in with the Version 4.0 but cannot be used by Interbase Users) and Schedule Analyzer for the Enterprise.
  7. 0
    Yousif Alaubidi ·
    Dear Ronald Winter

    Thanks for youe advise

    with best regrds