My first programme. Need Help

Mon MelendresMember for 15 years 3 months
Created
10
6
0

Dear All,

 

I just want to have feedbacks from you guys regarding my programme (using P3, Water Pipeline Project). I have no one to consult to. Surely i'll appreciate your feedbacks greatly. I am not sure what are my mistakes, improvement and suggestions regarding my programme. thanks thanks.

Note: I am not sure also of my critical path as it shows only those activity that are latter part of the project????? (since other major activities are shown in earlier part) 

here's the link in compressed file.

http://www.filedropper.com/e346

 

thanks in advance,

mon melendres

mon.melendres@yahoo.com

10 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Mon I could not open your

    Hi Mon

    I could not open your link so this will have to be basic stuff.

    Is your pipeline above ground or underground?

    What size pipe and how long?

    What material - steel or concrete?

    How many  crews?

    And for a start P3 is the wrong software - you need a time distance programme such as Tilos or PowerProject in task-per-line mode.

    Best regards

    Mike Testro

  2. 0
    Mon Melendres ·

    MikeThe project is an

    Mike

    The project is an underground pipeline about 100 km long (located on various areas of Doha) with the cost of roughly 28 million USD.

    The material is DIP.

    My programme is yet to complete. The scheduling is finished, I have yet to load cost and resources.

    P3 is the only programme i must use.

    I open the link myself and there's no problem downloading file at all.

    Hope to have your insights regarding this.

    Many thanks,

    Mon

  3. 0
    Justin James ·

    Hai Mon.I opend your file ,

    Hai Mon.

    I opend your file , and gone through it , since me too working in a similar project in doha , i found some loggical errors , like sterization & then connect to existing , 6 bar tesing is not included , Hdraulic swabbing should follow Iniial testing , Re-check your "Enginnering" activities . KAHRAMAA needs minimum of 7 days of review for major items , Under closeout , u cannot keep the milestone.1 asbuilt in general  , contractually it should come under Muaither Area & Muraikh Area seperately.

    If u need any further assitance , send me an email sjustinjames@gmail.com

    Regards

    Justin,

  4. 0
    Mon Melendres ·

    Justin,Thanks you very much.

    Justin,

    Thanks you very much. It's nice to hear that we're working on similar project.

    Yeah, I realized your insights. But how about the critical activities that reflects only those latter part of the project, is it normal????

    Thanks again in advance.

     

    Mon

  5. 0
    Justin James ·

    Mon,yes it is normal with

    Mon,

    yes it is normal with pipe line projects, as long as u acheive the planned progress for the paricular month , u'll not face diffculties at the end.

    Regards

    Justin

  6. 0
    Mon Melendres ·

    Justin,thanks again. u'r

    Justin,

    thanks again. u'r insights are deeply appreciated.

    God speed. 'til nxt time.

    Regards,

    Mon

  7. 0
    Mike Testro ·

    Hi Mon Justin is giving you

    Hi Mon

    Justin is giving you good technical advice so I wil not try to add to that.

    Since you are using P3 I assume that you are using SS Links with some lag - which is why your critical path will be distorted.

    If at all possible try to break the work down into small spreads - at least between major structures such as pumping stations and crossings.

    Try to use FS links if possible - if not then make sure you have a FF link to balance each SS.

    Beware of structures - particularly with piled foundations with a 28 day curing period for the test pile.

    It is most likely that your true critical path will go through the structures - not the pipeline.

    Allow for a shorter working day during Ramadan and peak temperatures.

    With automatic welding you can expect up to 500m a day production - semi automatic up to 200m per day.

    BTW I have just completed a detailed programme for a 120km gas pipeline using AstaPower project - it took me 90 minutes including all structures and crossings and welder resourced.

    Best regards

    Mike Testro

  8. 0
    Mon Melendres ·

    MikeGot your point regarding

    Mike

    Got your point regarding balancing of pred, yeah i'll modified my programme, i think FS will result more smooth.

    Great advice, thanks.

    Mon

  9. 0
    James bid ·

    hi mon, I  am also doing a

    hi mon,

    I  am also doing a underground services and maybe the structure that i pasted below might help you.

    I have some pointers as follows:

    1. MAybe you could include your company initial in your activity id to distinguish the ownership of your program

    2. you must define what are your preliminaries, consultant might ask you the breakdown.

    3. i found Concrete mix design? is this for chamber? or for concrte blinding prior to chamber?

    4. is your chamber cast in situ? i found delivery of precast chamber(DEL 04) and construction of chamber( MUA 09)

    5. maybe delivery of pipes and fittings should be one activity

    6. In my view, all material procurement activity should be present in construction activity i.e, pipes and fittings- pipelaying, i found heat shrink material and corrosion protection in your engineering, where is this in your construction activity? pipe wrapping?

     

    hope will help,

     

                 
    Preliminary        
      Key Milestone      
        General      
          Project start    
          Notice to proceed    
          Project complete and Hand over
        other milestone    
          drawing received    
                 
                 
    Engineering        
      Construction drawing    
        Muaither south    
        Muraikh       
        Other area      
      Shop drawing      
                 
      Detailed drawing      
                 
      As built drawing      
                 
    Procurement        
      Material Management    
        General      
          Pipes & Fittings    
          Concrete material(mix design)
          Bedding & surround material  
          Valves      
          Flow meter    
          Chamber cover frame  
          warning tape    
      Material Procurement    
        General      
          pipes po    
          pipe lead time    
          pipe delivery on site  
                 
    Construction        
      Zone 5S        
        Muaither area    
          Excavation    
          Gravel Bedding    
          Pipe wrapping and laying  
          Hydraulic swabbing  
          Concrete blinding and chamber placing
          Valve Installation    
          Pipe Testing    
          Gravel surround     
          Partial Backfill & Warning tape
          Backfill to GL    
          Coonection to exiasting and sterilization
          Reinstatement    
        Muraikh area    
                 
                 
        other area      
                 
                 
      demobilization      
                 

     

  10. 0
    Mon Melendres ·

    James,your breakdown is a bit

    James,

    your breakdown is a bit hard but i think it is quite impressive. thanks. i'll try it should there be any re-programming.

    Regards,

    Mon 

Log in or join to reply