COLOUR GRAPHS

Forum GuestMember for 17 years 8 months
Created
2
2
0
Can we get colour graphs - histograms, resource curves in P3

2 replies

Oldest first
  1. 0
    Ismail Vandeliwala ·
    Yes we can.

    Just change the pen value in the graphic reports - Pen.
  2. 0
    B Cass ·
    Under the PEN tab in the graphic reports options there are two places to change colors. The Pen column is for lines and bar outlines. The Fill Pen column is for bar fill color. Default P3 colors are as follows:

    1 = Black
    2 = Red
    3 = Blue
    4 = Green
    5 = Purple
    6 = Cyan
    7 = Yellow
    8 = Orange
    9 = Brown
    10= Maroon
    11= Teal
    12= Dark Green
    13= Dark Blue
    14= Violet
    15= Dark Teal

    Probably more information than you wanted.