where can i find a software to convert microsoft project to p3 vice versa?

6 replies

Oldest first
  1. 0
    Muhammad Ali ·
    Well Haslan :

    Often I need to switch between P3 and MS project. I was facing the same trouble using MS project 2002 becuase it doesn’t have this option!!. Then parallel to this I started using MS project 98 which has this conversion option. How come the latest version is not having this facitltiy I don’t know even !! Friends let’s discuss this now . . .

    Sentence deleted by moderator

    Regards
    Muhammad Ali
    PP Id 7575
    UAE
  2. 0
    John peter ·
    Deleted by Moderator


  3. 0
    Muhammad Ali ·
    Deleted by moderator
  4. 0
    Paul Harris ·
    Try this thread:

    RE: conversions to P3
  5. 0
    Paul McCarthy ·
    Gents
    Since MSP helpfully decided not to allow you to ’save as’ MPX, you can either open your Project file in MSP’98 (assuming you still have a spare copy) and then save it as MPX, or,
    P3 have written their own routine which is freely available on the knowledgebase, extract given below:
    Hope this helps
    Cheers
    Paul

    The following is a Primavera Knowledgebase solution:
    Solution ID: 200316155826

    Goal How to use the MPP to MPX Utility.

    Fix Primavera provides a utility to convert Microsoft Project MPP files to MPX files. MPX files can be converted to P3 files. MPP files can not be directly converted to P3 format. To use the utility, Microsoft Project must be installed on the computer.

    NOTE: P3 does not need to be installed to run this utility.

  6. 0
    Mk Tse ·
    Just a reminding note.
    Any client machine install this MPP to MPX conversion utility must have Project installed.