Conversion of PRX file to MPX file

Ozan KoseogluMember for 19 years 10 months
Created
6
1
0
Hi,
I have an PRX file and need to convert it into MPX file and open it in MS PRoject. However, I do not have Primavera (p3) programme or do I need P3 programme for such a conversion. Is there a way to do this without having Primavera programme?
Thanks
Ozan

6 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    PRX file is a compressed backup file generated by Primavera P3; as far as I know, the only way to open it and restore the P3 files is to use the restore command in P3.
    Then you will convert the P3 schedule by using the P3 to MPX converter within P3
    Alexandre
  2. 0
    Dayanidhi Dhandapany ·
    you don’t need to have P3, you can look for PRMCONV.exe file of 1.9mb size. that is sufficient to convert your PRX file to compatible with MSP.

    HTH
  3. 0
    Alexandre Faulx-Briole ·
    Is it really possible to convert a PRX file with PRMCONV.exe?
    Mine is only reading the xxxxxxxx.P3 files
    Alexandre
  4. 0
    Dayanidhi Dhandapany ·
    Hi Alex,

    I interpreted the question wrongly, sorry for that. It is not possible to convert PRX file to MPX without restoring it first in P3.

    Cheers!!!

    Daya
  5. 0
    Paul Harris ·
    To restore a P3 *.prx file one does not need P3, you just need to change the extension to *.exe in explorer and double click on it and it will self extract.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  6. 0
    Dayanidhi Dhandapany ·
    Excellent Suggestion, it works well.