Infomaker and P3 - View report error

Hafedh Ben AliMember for 23 years 7 months
Created
2
1
0
Can anyone help me in resolving this error which appears when I try to run a report from Infomaker in P3, even a sample one :(( Select error: sql state= S002 [intersolv][ODBC Btrieve driver] table not found in data dictionary: APEXDIR ))
Thanks

2 replies

Oldest first
  1. 0
    Dayanidhi Dhandapany ·
    Make sure to create FILED.DDF, FILE.DDF, INDEX.DDF files from Tools->Update Data Dictionary -> Clicking Advanced from P3 Data Field Option. Then when you open Infomaker, you can link this file accordingly in the ODBC area. i.e In the Data Source Name, give a reasonable project title to recognize, then in the database directory enter a proper path where the .DDF files stored.

    Hope this will help..........
  2. 0
    Hafedh Ben Ali ·
    Thanks to Dayanidhi, it works, encourage P3 users to use this utilities to refine their reports.