Weekly progress report
In the Open Standard
Richu RoseMember for 19 years 8 months
- Created
- 11
- 3
0
Dear Planners,
I am new in planning , having started my carrer as a planner in Nov’06. I am a planner by chance & not by choice. As one of planner was leaving , i was told to take over. I have no formal training on P3 3.1 or any other planning & scheduling software.I have gained sufficient knowledge through this forum & Paul Harris book. Prior to Nov’06 i was on site execution.
Friends I have to submitt weekly report containing following details :
1) Activity ID
2) Activity Description
3) Total % weightage
4) Percentage work done
a)Completed untill last week
b)Work this week
c)Cummulative
5) % weightage
a) Planned till this week
b) Actual till this week
c) Varience
Friends, can anyone show me the steps / procedure in generating a tabular report in P3 3.1
Thanking for all the good work done through this forum.
Richu
I am new in planning , having started my carrer as a planner in Nov’06. I am a planner by chance & not by choice. As one of planner was leaving , i was told to take over. I have no formal training on P3 3.1 or any other planning & scheduling software.I have gained sufficient knowledge through this forum & Paul Harris book. Prior to Nov’06 i was on site execution.
Friends I have to submitt weekly report containing following details :
1) Activity ID
2) Activity Description
3) Total % weightage
4) Percentage work done
a)Completed untill last week
b)Work this week
c)Cummulative
5) % weightage
a) Planned till this week
b) Actual till this week
c) Varience
Friends, can anyone show me the steps / procedure in generating a tabular report in P3 3.1
Thanking for all the good work done through this forum.
Richu
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?