INDIVIDUAL PROGRESS
In the Open Standard
Hemanth KumarMember for 23 years 11 months
- Created
- 1
- 3
0
PLANNERS
I AM DOING A LUXUARY YACHT PROJECT
’BASE LINE’ -WAS PREPARED BASED ON THE CONTRACTUAL TIME PERIODS
THE PROBLEM IS ,ALL THE DRAWINGS WERE TO COME FROM GERMAN
NAVEL ARCHITECTS
WE ARE GETTING DRAWINGS PART BY PART ie ONE CABIN THIS WEEK SECOND CABIN ONE WEEK LATER ETC.
NOW THE MANGEMENT WANTS HOW THE WORK OF INDIVIDUAL CABINS AFFECTED DUE TO THIS. ie CONSIDERING DRAWING RECEIPT DATE
AS THE START DATE OF A PARTICULAR CABIN HOW MUCH PROGRESS WE ACHIEVED AND HOW MUCH SHOUD HAVE BEEN THE PROGRESS AT A GIVEN TIME. I DONT WANT TO BREAK THE PROJECT IN TO DIFFERENT SEGMENTS AS I HAVE ADDED ALL THE RESOURCES AND MANAGEMNT REQUIRES THE RESOURCE REQUIREMENT DETAILS TIME TO TIME FOR THE WHOLE PROJECTS.,I DONT HAVE P3e/C ANY SOLUTIONS IN -P3
I AM DOING A LUXUARY YACHT PROJECT
’BASE LINE’ -WAS PREPARED BASED ON THE CONTRACTUAL TIME PERIODS
THE PROBLEM IS ,ALL THE DRAWINGS WERE TO COME FROM GERMAN
NAVEL ARCHITECTS
WE ARE GETTING DRAWINGS PART BY PART ie ONE CABIN THIS WEEK SECOND CABIN ONE WEEK LATER ETC.
NOW THE MANGEMENT WANTS HOW THE WORK OF INDIVIDUAL CABINS AFFECTED DUE TO THIS. ie CONSIDERING DRAWING RECEIPT DATE
AS THE START DATE OF A PARTICULAR CABIN HOW MUCH PROGRESS WE ACHIEVED AND HOW MUCH SHOUD HAVE BEEN THE PROGRESS AT A GIVEN TIME. I DONT WANT TO BREAK THE PROJECT IN TO DIFFERENT SEGMENTS AS I HAVE ADDED ALL THE RESOURCES AND MANAGEMNT REQUIRES THE RESOURCE REQUIREMENT DETAILS TIME TO TIME FOR THE WHOLE PROJECTS.,I DONT HAVE P3e/C ANY SOLUTIONS IN -P3
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?