Calculating Overall Planned Progress
In the Open Standard
Kamran HaziniMember for 21 years 9 months
- Created
- 6
- 3
0
Hi there;
My client is asking me to provide them with a report, including planned perecent complete and actual %complete for each activity and overally.
I defined a report in Report Writer to calculate planned perecnt complete by this formula: BCWS/BQ. Now the problem is that this way works for all activities perefct but the overall planned progress could not be calculated and P3 added all these figures for all activities instead of calculating the formula for overall project. I can ask my cleint to devide the overall BCWS by overall BQ manually but I think it is not very convenient.
Did anybody encounter this problem before or any solution for that?
Thanks
My client is asking me to provide them with a report, including planned perecent complete and actual %complete for each activity and overally.
I defined a report in Report Writer to calculate planned perecnt complete by this formula: BCWS/BQ. Now the problem is that this way works for all activities perefct but the overall planned progress could not be calculated and P3 added all these figures for all activities instead of calculating the formula for overall project. I can ask my cleint to devide the overall BCWS by overall BQ manually but I think it is not very convenient.
Did anybody encounter this problem before or any solution for that?
Thanks
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?