Skip to content

How to progress-Piping Instalation

Carmen ArapeMember for 22 years 3 months
Created
5
1
0
Piping Instalation-Large Bore & Small Bore- Progress measurement

Progressing the activity instalation, I have the following question:

Milestones were defined to progress the work. For each Milestone I need a quantitiy estimate to track the progress as follow: executed quantities/total estimate. My question is: what type of estimate I should have for each milestone such as:
Erect&fit up: Equivalent linear meter (straight lines+spools) / total equivalent linear meters.
Welding : welded inches / total inches.
Pipe suport : units of supports / toatl supports to be installed.
Test : No idea
Valve install.: installed valves / total valves

Appreciate any HELP
Thanks
Carmen (working at Construction SITE in Venezuela)

5 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Hi Carmen send me our email addres (need to send 2 x 5 meg file) this is a book that wil help you I would suggest manhurs

    Jaco Stadler

    (jaco.stadler@snclavalin.comO
  2. 0
    Andrew Podolny ·
    Hi carmen
    We’re using meters as unit of measure for hydraulic testing of pipeline. Testing is performed by sections (i.e. from one block valve to another). Usually it takes some time to fill the pipeline by water and to gain the testing pressure (depending of the length of the section and DN) plus 24 hours for retention.
    When testing particular assembly unit (ball valve for instance) the right unit of measure is psc.
    Hope it’ll help.
    Best regards,
    Andrew
  3. 0
    Carmen Arape ·
    Hi Jaco

    My E-mail is cararape@cantv.net and I would like the book that you mentioned. I am controlling an EPC lump sum contract and the contractor is using man-hours for weighting the lines by AREA and quantity estimates for each progress milestone.

    Lot of Thanks
  4. 0
    Carmen Arape ·
    Hi Andrew

    When you mention meters by sections,it looks like easy for straight sections, but how do I do with spools ? Should I include them or not?.

    Thanks, Carmen
  5. 0
    Raj Maurya ·
    Carmen,
    As you said you are controlling LSTK EPC, you no need to monitor the progress on MH instead I suggest you to use inch-Dia for fit and inch-meter for erection and same for hydrotesting.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?