How to progress-Piping Instalation
In the Open Standard
Carmen ArapeMember for 22 years 3 months
- Created
- 5
- 1
0
Piping Instalation-Large Bore & Small Bore- Progress measurement
Progressing the activity instalation, I have the following question:
Milestones were defined to progress the work. For each Milestone I need a quantitiy estimate to track the progress as follow: executed quantities/total estimate. My question is: what type of estimate I should have for each milestone such as:
Erect&fit up: Equivalent linear meter (straight lines+spools) / total equivalent linear meters.
Welding : welded inches / total inches.
Pipe suport : units of supports / toatl supports to be installed.
Test : No idea
Valve install.: installed valves / total valves
Appreciate any HELP
Thanks
Carmen (working at Construction SITE in Venezuela)
Progressing the activity instalation, I have the following question:
Milestones were defined to progress the work. For each Milestone I need a quantitiy estimate to track the progress as follow: executed quantities/total estimate. My question is: what type of estimate I should have for each milestone such as:
Erect&fit up: Equivalent linear meter (straight lines+spools) / total equivalent linear meters.
Welding : welded inches / total inches.
Pipe suport : units of supports / toatl supports to be installed.
Test : No idea
Valve install.: installed valves / total valves
Appreciate any HELP
Thanks
Carmen (working at Construction SITE in Venezuela)
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?