Hi
Would like to know what excatly is methodolgy to be adpoted for carrying out revision in the target schedule.
I mean , say a contract gets a time extension of original project for carrying out some addtional work. Do we have to give target schedule for the whole project or only for the remaining scope of work along with additional allocated work.
Recently i submitted revised schedule for one project having same case . I presented new target as revised updated schedule till that data date. Consultant commented that original target with new scope to be first submitted . Is that true. Can it be done and will that be logical as many events may not have happened as per original target schedule. All , please provide ur valueable comments.
Regards
Anil
Would like to know what excatly is methodolgy to be adpoted for carrying out revision in the target schedule.
I mean , say a contract gets a time extension of original project for carrying out some addtional work. Do we have to give target schedule for the whole project or only for the remaining scope of work along with additional allocated work.
Recently i submitted revised schedule for one project having same case . I presented new target as revised updated schedule till that data date. Consultant commented that original target with new scope to be first submitted . Is that true. Can it be done and will that be logical as many events may not have happened as per original target schedule. All , please provide ur valueable comments.
Regards
Anil
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?