User Defined Bars in P3

Emmanuel UdoMember for 22 years 8 months
Created
1
1
0
Hi folks,
Can somebody out there advise me on how to define and apply user-defined bars in P3.
I know Paul Harris posted something on this sometime back, but I cannot find it.
I have defined one and attempted to apply it but it did not work.
Please, this is urgent.
Many thanks for your help.

Emmanuel

1 reply

Oldest first
  1. 0
    Steven Oliver ·
    2 methods.

    1. For individual bars, highlight required bar. From the menu options choose, Format, Selected Bars, Modify Bar Format. This format can then be copied and pasted onto other bars.

    2. To format bars based on a code value. Format, Bars, Pattern.

    HTH