Skip to content

Summarized Float

Rajeev KumarMember for 23 years 5 months
Created
3
1
0
Can someone tell me what does the summarized float mean?Any help would be appreciated. Thanks

3 replies

Oldest first
  1. 0
    Daniel Limson ·
    Summarized float would be the total float available to your project, again which means the total aggregate number of days you can delay a project without affecting your completion date.

    Regards,
    Daniel
  2. 0
    Philip Jonker ·
    Hi Guys,

    As I have never heard this term, I had a look in the help menu. This topic is actually covered in the P3 Help menu, under "How P3 summarizes data". Apparently you can set some options. I would say that if a group of activies is summarized, the summarized float should be that of the activity with the least float in the group. Therefore I would set the option to "most critical dates".

    Lets hear some other opinions on the subject.

    Regards,

    Philip
  3. 0
    Frank Borcherdt ·
    When you summarize data using format organize, P3 also keeps track of the earliest calculated early start, earliest calculated late start, latest calculated early finish and latest calculated late finish for that group of activities. Philip is right that there is an option to determine how the total float is calculated BUT be very careful before you change it from finish dates (the default method used by most software including SureTrak) as it will apply it to all activities as well as the summaries.

    If you leave the option on finish dates it’s the latest calculated late finish for that group of activities less the latest calculated early finish for that group of activities, on start dates it’s the different between the start dates, most critical is the smallest of the start or finish float.

    As long as you understand that it applies to float calculations at both the summary and detail levels chose the method that suits your particular circumstance. I tend to leave it on finish dates for compatibility with other products including Suretrak.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?