Rajeev KumarMember for 23 years 5 months
Created
18
1
0
Hi guys,

Can somebody show me a way in which I can show a specific colour in a summarized bar for a specific code. I know how to do it for individual bars, but when I summarize it, it takes the colour of the bar assigned for individual bars in format ,bars.

Can somebody help?

PS. I use p3 3.1

18 replies

Oldest first
  1. 0
    Alex Wong ·
    Rajeev

    Thats how you do it with patterns display according to the activity code value


    Select Format - Bar
    in the lower left hand coner you will see a button call Pattern Select that it will open another windows
    In the new windows you can select the activity code you want to assoicate with the patterns
    then you can assign the actual code value to a particular patterns

    This is a smart way to assign the patterns to a code value

    Cheers

    Alex
  2. 0
    Rajeev Kumar ·
    Thank you for your help, Alex & Bill.

    I know how to assign patterns to "individual" bars, according to codes, what I need to know is how we can show codes on a "summarized" bar.

    or pardon me if I am not understanding your answers correctly.

    cheers
  3. 0
    Alex Wong ·
    Very Similar steps

    Format - Bar
    Modify Button
    Label Tap
    "+"
    Location of your project code "Left, Right Center"
    Then
    Select your code
    And Size of the font

    Cheers

    ALex
  4. 0
    Alex Wong ·
    The only way to display anything in summary bars is to set up display individual bars

    To do that
    Format - Summary Bar - Individual Bars

    However, I would never use that format because it is very messy
    Try to use organise to display your group coding is a lot more tidy

    Cheers

    Alex
  5. 0
    Sukumaran Subaramaniyan ·
    Hi,

    You also can display the activity codes in grouping bands.

    Go to Organize > Options. Mark the following checkbox for bar area:
    1) Display group divider as bands
    2) Text as value + description

    Activity codes with the description will appear in a band at gantt chart area.

    Regards.
  6. 0
    Rajeev Kumar ·
    Sorry guys, I think I put my question wrongly again.My requirement is to show a specific colour for each code "value" on a summarized bar. Suppose the summarized bar consists of activities of only one code "value", then it shows only one colour in the summarized bar. Suppose my summarized bar consists of activities with two different code values, then my summarized bar should show two colours, one for each code "value".

    Once again sorry for not stressing about code "value" in the previous mail.

    Cheers
  7. 0
    Dayanidhi Dhandapany ·
    Rajeev,
    I don’t understand your question rajeev, in summarized bar(grouping of similar activities) how can you show two different codes?. explain me further to understand your question.

    Cheers!!!

    Daya
  8. 0
    Jagadish E M ·
    Rajeev,

    Good question. But, I don’t understand why you want the bar to display all those colours when you are summarising the whole set of activities !!

    well I am sorry,I don’t have the answer for you but, definitly would like to know how it helps.

    cheers
  9. 0
    Dayanidhi Dhandapany ·
    Rajeev, I got your question now. Yes it is possible to display different colors for the same type of summarised activities.

    for example,

    If you apply pattern color for Area/Department and summarize the responsibility band(before u have to do the adjustment in the setting as Alex suggested)you can see different colors aligned in the same line. It is a good presentation really to see same discipline people working at different locations as a single bar(with interruptions if applicable).


    Cheers!!!


    Daya
  10. 0
    Alex Wong ·
    Daya

    I think it cannot be done in that way to a summary bar - individual bar yes but not summary bar. Like you cannot assign 2 value to a single activity

    Please verify

    Alex
  11. 0
    Rajeev Kumar ·
    I will explain my requirement with a detailed example,

    Suppose I have a multi-story building program, organized by floors. Under each floor, say I have 3 activities, Blockwork, plaster and paint. Say the activities names are 4th floor Blockwork, 4th floor plaster, 4th floor paint.Each of these activities are coded with an activity code called "ITEM" which has code values Block, plaster and paint.

    What I need to see is, when I summarize the program by floor, the summary bar for the 4th floor should have colours alligned side by side according to the code values, like suppose if blockwork works from day 1 to day 10, plaster works from 11 to 25 and paint from 26 to 30, I would like to see a red colour from day 1 to day 10, blue colour from day 11 to day 25 and green colour from 26 to 30 on the summary bar.

    I think I got it, but it looks well only if we dont have overlapping activities.

    I hope its clear now.
  12. 0
    Razi Khan ·
    Three different colors in one summary bar. It is not possible in P3.

    For such colorfull reporting I would use Excel.

    Cheers
  13. 0
    Jaco Stadler ·
    Hi Rajeev
    You are trying to create a line of balance.
    See previous I Would suggest you have a look at software on the market. Example Chainlink etc.
    Chainlink does have a 30 Day Trail Download and is intergradable with P3.

    Cheers
    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=9151
  14. 0
    Dayanidhi Dhandapany ·
    Dear Alex,

    Leave me your email id, or send a message to plannerdaya@yahoo.com i will send the screen shot of P3(Out put).

    What i did, i followed your suggestion in the settings for the individual bar and summarized at higher level(after applying code values), the higher level will show summary of different individual bars of same group of course aligned in the same level but with different colors.

    Cheers!!!

    Daya
  15. 0
    Razi Khan ·
    Sorry Rajiv

    My observation was wrong. You can do it exactly what you want provided no overlapping of activities otherwise Summary bar will split into many bars at different level.

    I tried your example. 4th floor activites Blockwork, Plaster and Painting Works. Format all three activity bars with 3 different colors. Then summarize at 4th floor I got Summary bar with 3 different color showing respective durations for each activity.

    But when Plaster overlapped with Blockwork than Summary bar splitted into 3 bars at aligned at different level but showing activity duration and colour.

    I followed this sequence Format>Summary Bars>Individual bar(any option).

    Cheers.
  16. 0
    Rajeev Kumar ·
    Thanks Razi and all others.

    I guess thats the only way to do it in P3.
  17. 0
    Alex Wong ·
    Daya

    my e-mail is alexwong6661@hotmail.com

    Cheers

    Alex
  18. 0
    Alex Wong ·
    Rajeev

    As I stated if you use that option "Display Summary indiviual bar will look very untidy. and its all over the place. Better stick with the organise view.

    Cheers

    Alex

Log in or join to reply