change hourly planning unit to daily planning unit
- Created
- 14
- 5
14 replies
Oldest first- 0PJPhilip Jonker ·You must export the original and remaining durations, as well the relationships. Export the data to Database (.DBF) format. Once you have copied the program into a day unit program, you need to check the calendars, ie how many hours per day was allowed for every calendar. You need to set up the day calendar in the new schedule. You then need to divide the durations in the file you exported by the number of hours allowed by the calendars. You then need to do the same in the exported relationship file for the lags. Once you have done this import these new durations and lags into the schedule. It sounds a bit complicated, but it is fairly simple. Should you need more help, just ask.
Regards - 0FBFrank Borcherdt ·You could also do the copy and then use Global Change to update the durations and lags. Duration and lag may also exist on resource assignments, so export/global change these as well. P3 uses the calendar from the predecessor on relationship lags and this can present a challenge when multiple calendars with different hours per day are in use.
By far the easiest method is to use Primavera SureTrak (if you have access to it) as it allows you to change the option from hourly to daily and save the schedule. If you have multiple calendars with different hours per day, you need to do a careful review.
- 0JSJaco Stadler ·Yes I have an Idea
1) Check to see if the files are not Marked Read Only.
2) Try P3 Help
It gives you a step by step explanation as to how to copy a File. Or a Project Group.
3) If all of This Fail Try run Fix It on the P3 File. (PFWX)
4) Also Try and Work on your C Drive. Once you have completed then you can move it back to the network
Cheers
The Above should do the trick
- 0PHPaul Harris ·To copy a project you need to fill in the Project Group Field and not the Project Name field.
The easiest way to change the unit of a P3 file is to open the project with SureTrak and change the time units in the options form. 8 hours/day are converted to days and will not work for calendars that are not 8 hours/day.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
- 0PJPhilip Jonker ·Hi Paul,
As the Guru, nice to see you participating. This particular subject has been discussed at length in other threads, and particularly the problem of calendars. An area that is not taken into consideration is relationships ( not with sheep) but particularly the lags, a great deal of consideration to detail has to be paid to everything in the schedule when doing conversions. Try to teach the practical implications. There is ten ways of skinning a cat or croc, but approaching a sheep is limited, to carefully.
- 0SZShima Zabetian ·
Hi, guysI have a problem in
Hi, guys
I have a problem in this subject:
When I change the planning unit from hour to day, P3 omit some decimals in original duration and cause diffrent activity dates, how can solve this problem?
Can I use hour as planning unit and just make P3 to show durations in day?best regards
Zabetian
- 0AFAlexandre Faulx-Briole ·
Zabetian,no, you cannot
Zabetian,
no, you cannot schedule your project in hours and have P3 display durations in, days, as P3 only have ONE planning unit
the only way to change the planning unit when using P3 (I do not mention SureTrak; refer to Paul Harris post for that) is to COPY your project to ANOTHER project:
Tools, Project Utilities, Copy
Select the new planning unit you want
Be aware that P3 will only change the planning unit, it will not calculate hours in days or vice versa; use Tools, Global change to calculate the new activities duration
Alexandre
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?