Planning using Meters - P6 - NATM Tunnel
In the Open Standard
Shane StanfordMember for 17 years 11 months
- Created
- 10
- 4
0
Hi guys,
Im new to P6 and planning, I am working on a Tunnel job in the UK and would like to show meterage on P6, for example -
Week 1,2,3 and 4 - 42 meters of tunneling is predicted each week, but week 5 only 36m because of bad ground expected. Is there a way I can manage progress like this and show it on P6?
The only way I can seem to manage this is by using excel spreadsheets, but id rather keep it on one software program.
Thanks
Im new to P6 and planning, I am working on a Tunnel job in the UK and would like to show meterage on P6, for example -
Week 1,2,3 and 4 - 42 meters of tunneling is predicted each week, but week 5 only 36m because of bad ground expected. Is there a way I can manage progress like this and show it on P6?
The only way I can seem to manage this is by using excel spreadsheets, but id rather keep it on one software program.
Thanks
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?