Skip to content

Discripency p3 Screen and Report

Azvi HanifaMember for 22 years 1 month
Created
6
3
0
Hi Planners

I have big confuse that my project contain over 900 activities, project started June 04, in recent update i have seen that BQ in p3 Screen and report produce by P3 and Excel are shown different why it is? If any explain what will the reason I would be much appreciate

Thanks.

Azvi

6 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Hi

    Please define which reports you are running.

    Cheers
  2. 0
    Azvi Hanifa ·
    Jaco Stadler

    I have to produce s- curve for the latest updated schedule which i have received from the contractor, S-curve to be produce based on the effort, In the program all the resources unites are in man hour.

    I have seen B.Q in the p3 screen and tabular report has different value.

    could you advise me what will be the issue?

    Best Regard
    Azvi
  3. 0
    Jaco Stadler ·
    Hi Which Reports are you talking about.

    Maybe you have applied a Filter
  4. 0
    Jaco Stadler ·
    Azvi

    I am going to make some assumptions.

    You are talking about Earned Value.

    You are using RT-01 Report.

    You need to check the following.

    1) Filters
    2) Data Date / Time Period
    3) Also remember when p3 exports it works with period beginning.
    The Value in your P3 Screen BQWP (Earned Value Should be the correct value)
  5. 0
    Azvi Hanifa ·
    Hi

    Jaco Stadler

    I m not concern about the type report, my concern is why same date item ( Budget Quantity )shoes different value in p3 refold screen and the resource tabular report

    Thanks
  6. 0
    Jaco Stadler ·
    Are you looking at the same thing ?????

    If we don’t understand what you are looking at we can not tell you what is wrong. If we dont understand what is wrong then the only advice we can suggest is to hire a qaulified planner who can do the job.

    Tell me have you had a look at the Filter and Resource selection are they the same on both screens. (Remember a filter has more than one lvl.)

    When you export what method do you use are you exporting a report that is based time or on actualy value.

    You see you need to be specific.



Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?