PIVOT TABLE

Sunil KumarMember for 21 years 6 months
Created
5
2
0
CAN ANYONE TELL ME IN DETAIL THE USE OF PIVOT TABLE IN EXCEL WHICH I BELEIVE IS XCELLLENT FOR TRACKING ENGINEERING IN A PROJECT.

THANX

Sunil

5 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    msah el kheir,
    with a pivot table, you can fix some kind of 3D table where tasks and resources are alternatively shown as rows and columns and work / cost are summarized in the inner cells.
    difference from a classical table is that Excel pivot table is dynamic, i.e. you can move the row headers to columns and vice & versa
    have a look at Excel online help, it is most usefull
    good luck
    Alexandre
  2. 0
    Andrew Podolny ·
    Hi there.
    Here is online tutor
    http://www.contextures.com/xlPivot01.html
    (See the bottom of the a.m. page for additional info)
  3. 0
    Dylan Wan, PMP EVP ·
    Here is a PivotTable paper found in the Constrcution Financial Management Association web site:

    www.cfma.org/documents/PivotTables.pdf
    http://www.cfma.org/pivot_dir.htm

    You can also get a sample spreadsheet from here:

    www.cfma.org/PIVOT.xls

    Hope this helps.
  4. 0
    Sunil Kumar ·
    Dylan, Andrew and Alexander,

    Thankyou very much, They were fantastic leads to findout on Pivots.
    Are there similiar sites on Access too...

    Regards

    Sunil
  5. 0
    Philip Jonker ·
    There is nothing like basics, pivot tables are nothing but bata bases and their indexes. Challenge