Activity table and bar chart not displayed

Hakim PlanningMember for 17 years 4 months
Created
1
1
0

Hi everybody,

I use P3 un my job, but recently when I open a project I can't see both the activities table at left (ACtivity ID, Activity description, ...) and the associated bar chart. I make a schedule, and on the report i can read all informations (Number of activities, progress, ...). This happened for all layouts and all projects both existed and created.

I've unistalled and reinstalled again the software, but the problem not resolved.

Please help.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    go to print preview then the

    go to print preview then the options tab then make sure that tables and bars is checked 

Log in or join to reply