Filter Activities with Lead/Lag

Kashyap MothaliMember for 21 years 6 months
Created
7
1
0
Is there any way one can filter activities with lead/lag? The only way I have been doing it so far is to look at the Pred/Succ dialog boxes.

7 replies

Oldest first
  1. 0
    Sukumaran Subaramaniyan ·
    Go to Custom Data Items and create a data base for Lag in Actvity Tab.

    Specify the following:
    Name = Lag
    Type = N
    Length = Specify the required length
    Description = Specify the required description

    Once completed, open a column for Lag in Activity Column. You got to do some editing manually. Key in the assigned lag for the particular activities. Then use Filter Command to filter activities with lag.

    Regards.
  2. 0
    Kashyap Mothali ·
    I apologize for not stating my requirement completely. I want to see lead/lags in a separate column. P3 will not allow me to do this.

    Kashyap
  3. 0
    Philip Jonker ·
    That is not possible to do as there might be two or more successors or predecesors to any one activity.

    The other way to do it is to export the successor relationships, to a .dbf file, and then to open this file in excel, where you can filter what you need. To do this you go to tools/project utilities/export, add an export report, and click on successor relationships, then under format put in the file path and name, and the file type as .dbf.


    Hope this helps.
  4. 0
    Sukumaran Subaramaniyan ·
    Hi Philip,

    Thank you for the information. Even i can make a changes on the lag and import it to update the P3 file.


    Regards.
  5. 0
    Philip Jonker ·
    That is correct, just make sure you save the changes to a dbf file. To avoid duplication of relationships, it is better to open a new project file, with only the activity information and/or resources information. This can also be done by exporting and importing. then you import the updated relationship file.

    PS. If you have MS Access, you can use that as well, if you want to link the relationships to the activity descriptions.
  6. 0
    Mohamed Hegab ·

    Schedule Cracker

    Schedule Cracker (www.schedulecracker.com) provides what you are looking for.  We identify lag through relationships, filter them or group activities by lag and much more.  Our powerful tool allows you to compare multiple schedules, trend project-performance values, and forecast project performance, and much more. 

  7. 0
    Rafael Davila ·

    Even low cost software as

    Even low cost software as Primavera SureTrak can filter for lag at a click of the mouse, without time consuming procedures.

    It is kind of limited as it does not displays nor filter for many lag parameters, among them lag calendar, a basic check for when your relationship lag is in calendar days while your connected activities have different work-days calendars.

    You can try the same strategy as with SureTrak, first organize by successors or organize by predecessors and then you shall be able to filter for a limited number of lag parameters, better something than nothing.

    Photobucket

    SureTrak cost us at street price half of MSP (~ 400 US$) and being a budget software is still able to identify if the activities are delayed by resource availability instead of by a logic link, similar to MSP.

    Good luck