Skip to content

Filter for work for today.

Ad BenMember for 19 years 10 months
Created
20
3
0
Hey, I need some help with a filter.
I want to be able to pop out a filter of my schedule that will show all work in progress AND what ever will start in the period. I am tying to make a one week schedule that will show all that is going to be going on this week.
Thanks for any help

20 replies

Oldest first
  1. 0
    Ronald Winter ·
    Ad,

    You question is software specific. I am afraid that you will need to share with us the platform you are suing to record your schedule.
  2. 0
    Ad Ben ·
    Yea I thought about that this morning. I am using P3 ver.3.1
    Thanks
  3. 0
    Tahir Naseem PMP, CCE ·
    Dear adben
    There is nothing like VBA / visual fox but we can resolve this matter like below
    Click the filter Icon or from format - > filter tthen press add
    “Activities in progress / new activities”
    in Select if tab
    Percent complete less then 100
    in second level
    early dates within range dd+0d lower limit and DD+7D
    now run
    from now whenever you run next time this filter it always give you the activities in progress and early start within next week
    regards
    Tahir
  4. 0
    Hemanth Kumar ·
    organize by early start
    select "day" as duration for banding
  5. 0
    Alex Wong ·
    Tahir

    Your filter is wrong

    Because the early dates cannot be within DD+0 to DD+7
    Simple if the activity is already started

    THe filter should look like this

    Precentage Complete <100
    AND
    ((Actual Start = Null and Early start Within DD+0 to DD+7)
    or
    (Actual Start <> Null and Early start less than DD+7))

    HTH

    By the way Hemanth

    if you want to display a one week lookahead is no use to organise by early start because all other activity will be displayed as well

    Alex
  6. 0
    Ad Ben ·
    This one is starting to make sense. With the others I am missing the ones that are already started.

    Ok now the dumb question.
    How do I get "Null" in there?
  7. 0
    Alex Wong ·
    blank
  8. 0
    Alex Wong ·
    I use this filter to filter out all my 1 month lookahead, 3 month lookahead and 6 month lookahead program.

    Good luck

    ALex
  9. 0
    Mk Tse ·
    If Actual Start is ignore in the criteria, the filter result may bee the same since PCT<100 already "cover"

    Don’t forget to schedule the project with revised data date (first day of the week)
  10. 0
    Alex Wong ·
    .mktse

    not quit right

    PCT<100 do is not necessary cover every activity

    PCT<100 is cover the activity that is Actually finished

    If you look closer there is two possibility that if activity actually started you need to pick up those activity started but not finish. and also the activity is not started but within the window period

    the filter i give should cover all scenerio

    and DD should cover the data date when you change your schedule

    HTH

    Alex
  11. 0
    Mk Tse ·
    Actal finished activity will have PCT=100 and RD=0 and an Actual date

    For PCT<100, the actual finished activity is excluded. However the software have the problem that accept the record that PCT=100 or RD=0 without input any Actual Finish Date.

    Recommend a practice to check the input data before do analysis or reporting
  12. 0
    Alex Wong ·
    You are half right but half wrong

    You can have a 100 completed activty without actual finish date
    but you cannot have a actual finish activity have less than 100% PCT

    Thats why if you looking a 1 week lookahead you dont want to see activity which is already finish 100% complete.

    .mktse please read carefully with my filter and try it yourself

    Good Luck

    Alex
  13. 0
    Tahir Naseem PMP, CCE ·
    Mr. Alex
    Sorry for late reply but i am surprise that why my filter not worked at your P3 i am running the same filter to update my schedule on weekly basis. You did not give any solid reason not to work.
    When we said the percentage less then 100 it mean it will select all activity not completed and there is no reasons you keep did not feed the actual finish date for the 100% completed activities.
    and when we said early dates it does not mean only early start, it looks also the early finish and so
    the filter pick
    all activity which is not start from early start with range
    and all started activities with early finish which are ultemately in the range even though the RD is 90 days.

    this filter work 100% accurate if some one has still doubt then i am able to send him privetaly the examples
    sorry if some experts get hurt with my comments

    Regards
    Tahir
  14. 0
    Mk Tse ·
    Alex,

    My practice is validate all data before analysis or reporting.

    Any activity with RD=0 or PCT=100 must have both Actual Dates earlier than data date. Any missing is not accepted.
  15. 0
    Alex Wong ·
    Tahir First thing first

    Ok

    YOur filter will not pick up activity that is started before the datadate but not yet finish . Got that??

    Cheers

    ALex
  16. 0
    Alex Wong ·
    then MK

    Have you try to progress your schedule using in the bar chart using the mouse to assign % complete, in there you can have progress the activity to 100% without puting a actual finish

    HTH

    Alex
  17. 0
    Mk Tse ·
    Alex,

    I know this one. That’s why I reject any activity with PCT=100 and AF is blank. Uncomplete data input is not accepted.
  18. 0
    Hemanth Kumar ·
    Organise By early start then select

    By Week Or
    By Day
    then

    New Page : YES


    Print What You Want
  19. 0
    Alex Wong ·
    .mktse

    what you said in your last posting is correct

    but your previouse posting have a different condition *&^


    Cheers

    Alex
  20. 0
    Alex Wong ·
    Hemanth

    I still think your method will not work because


    1. if you do not have filters you pick up all the actual finished activity (thats not what we wanted in a rolling programme)

    2. you will need to display all the months prior to the data date where you will have activity that had started but not yet finish

    3. you cannot use additional grouping because it will all over the place with so many grouping across different time period

    good luck and try to use a rolling programme filter....

    Alex

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?