target bar doesn’t freeze
In the Open Standard
Luca MeliMember for 21 years 5 months
- Created
- 4
- 1
0
Hello Guys
Today I copied my project and set the copied one as a target.
Now, when I compare the schedule with the target in the bar chart, what happens is that every time I change the remaining duration on my schedule it takes effect also on the target bar. If for instance I update the schedule and the remaining duration became less then the Original Duration then the schedule bar become shorter (fair enought) but what happens is that even the target bar get shorter following the schedule bar.
Looking at the P3 example it doesn’t happen. The target bar remain what it was fixed to be and the target ES and target EF do not change at all.
Should I check some rule to freeze my target bar?
Thanks
L.
Today I copied my project and set the copied one as a target.
Now, when I compare the schedule with the target in the bar chart, what happens is that every time I change the remaining duration on my schedule it takes effect also on the target bar. If for instance I update the schedule and the remaining duration became less then the Original Duration then the schedule bar become shorter (fair enought) but what happens is that even the target bar get shorter following the schedule bar.
Looking at the P3 example it doesn’t happen. The target bar remain what it was fixed to be and the target ES and target EF do not change at all.
Should I check some rule to freeze my target bar?
Thanks
L.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?