MPX Conversion

John ImpraimMember for 25 years 4 months
Created
4
20
0
Hi Guys,

How can I convert a project done in MSP 2003 to .mpx format, for subsequent conversion to p3 ?

Any help out there ?

Best regards

John

4 replies

Oldest first
  1. 0
    Hermie LaO ·
    Hi John,

    Contact Primavera. I do believe they have a conversion utility that converts MPX to P3 format.

    Just a plug! Open Plan can do it too! Both ways!
  2. 0
    Zhang Haixiang ·
    you may need some old version of Project e.g. MS-project 98
    Save your project as project98 format
    then use Project 98 to save it as MPX format.

    You may also find some third-part utilities to do the conversion
  3. 0
    Sukumaran Subaramaniyan ·
    Hi,

    You can download MPX2000 from www.sciforma.com to convert the MSP2003 to MPX.
    However, you still need to redo some work:
    a) reassign the calendar
    b) change the activity type from independent to task and milestone
    c) remove the summary bars
    d) etc.

    Regards.