filter for open ends !?

Mary JoAnnMember for 23 years 7 months
Created
1
1
0

I have got a EPC linked schedule. I want to delete all the Engg & Proc activities and just leave Construction in the schedule.

Obviously once I delete the E & P portion out, there will be many Construction activities without predecessors.

How do I filter out such activities from construction without any predecessors ?

Thankyou.

1 reply

Oldest first
  1. 0
    Dattatreya Padharthi ·
    It’s somewhat lengthy.
    Donot delete activities (E&P) initially. Export all activities (E&P) with successor relationship. You will get construction activities having atleast one Engg/Proc predessor.
    Take the successor column & add a temporary activity code (Please add the same code in P3 file).
    Import the file in P3 & select activities having this code.
    Those Construction activities are the ones without predessor (E&P).
    Please note that those activities having Constrn activities as predessor will also appear. (e.g Installation of Equipment will have , 1) delivery of eqpt & 2) foundation of Eqpt as predessor. So take this into consideration.

    Regards
    Dattatreya Sriniwas