Converting from p3 to msp

X PlannerMember for 24 years 4 months
Created
21
4
0
GUYS,

ANY POSSIBLE WAY TO CONVERT A 7K ACTIVITIES PROJECT FROM P3 INTO MSP PRESERVING THE SAME LAYOUT )CONSIDERING THE ASSIGNED CODES IN P3 AS A WBS IN MSP... ???

ACTUALLY I SUCCEDED TO CONVERT THE SCHEDULE DATA BUT THERE WERE NO WBS OR CODES IN THE LAYOUT AND THE DATA WAS NOT SORTED AS IN P3 WHICH WILL MAKE IT VERY HARD TO REBUILD A WBS SYSTEM FROM SCRATCH....


ANY IDEAS??????

THANX IN ADVANCE

21 replies

Oldest first
  1. 0
    Raj Maurya ·
    MSP generates automatic WBS that almost of no use. And there is no code structure in MSP but if you want to group or organise the activites you have to create custom fields but only for limited use.
  2. 0
    X Planner ·
    i agree with all of u guys ,but as hedge said some times the clint is very strong that will force u to do it his way even if it is the wrong way,
    of course i wouldnot want to convert 7k p3 project to msp but i have to and there is no any other way....

    so lets talk about it...
  3. 0
    X Planner ·
    i tried something thought that it might convert p3 codes to wbs in msp which was the p3e for construction but there was no luck...
    i got the same unorganized list of activities without any structure..
  4. 0
    Jaco Stadler ·
    Good Day

    Try This.

    Use MPX Conversion (P3 to MPX)

    Open up in MP

    Go Project - Group By - More Groups - New - Field Name Select - Text 1 (Your P3 Codes go into MS project text Fields)

    Once you have Organised Changed the Code to your P3 Code Description (Type & Copy Works)

    Now you should have the same Layout as in P3.

    But as to the Data I dont Know what got Lost

  5. 0
    Zhang Haixiang ·
    I have the experience of converting MPP to P3.

    save the MPP as MDB file,then select the data and save as dbf,make sure the field length is same as in P3

    then import into p3,you may do this several times to import all the data you want.

    I have not tried P3 to MPP, I think it can be done by import/export

    if you are to do this once a week or more often. You’d better write some code to do it.
    Project support VBA, so you can write some code in Project and using RA to read P3 data directly into Project
  6. 0
    X Planner ·
    Jaco,
    u said "Go Project - Group By - More Groups - New - Field Name Select - Text 1 (Your P3 Codes go into MS project text Fields)"

    Please Explain "your p3 codes go into..."
    u can not change the text name to the p3 codes unless it is included in the dropdown menu of the msp’s Field name

    my p3 codes:

    1- Area
    2- Building
    3- Location
    4- Level
    5- Part

    an example will be fine...
  7. 0
    Jaco Stadler ·
    Hi

    I must ask you something

    Have you converted the p 3 file to MPX ?

    Once you have opened the MPX file in MS did you look what is in the text fields ?.

    Cheers


  8. 0
    X Planner ·
    Jaco
    yes,
    and everything was converted successfuly except the id and the breakdown or the codes of course

    i just got a plain and unorganized list of activities.
  9. 0
    Jaco Stadler ·
    OK

    Insert the Text Field Column in MS Project. (In These you should see the (Old Code) Not Code Descriptions.

    Then you need to sort these by the (Codes) Copy & Paste the Description Over the Code (Or in Next Text Field)

    Then You Sort as I have explained.

    I Hope this helps

  10. 0
    X Planner ·
    Jaco ,
    if u r talking about the custom text fields in msp then No
    it has nothing to do with p3 codes

    but u might insert the same codes used in p3 in these custom fields and re-assign them to the activities which i donot want to go through.

    i appreciate ur help
  11. 0
    Jaco Stadler ·
    You do realise this generated autamtically in MS when you MPX Convert it. You dont have to do it manualy.
    Text10 = Old Act ID

    Cheers

  12. 0
    X Planner ·
    YEssss, Jaco

    It worked, my problem was that i converted through p3e so it generated mpp file and the text fields was empty, but when i converted it through p3 which produced mpx file i found all the codes in the text Fields,

    now it will be much easier for me

    thanx alot Jaco and all other contributers.
  13. 0
    Jaco Stadler ·
    Good Morning Planner Planner

    I am glad I could help. Where are you. What is the time their. Can’t be in New York. Posted at New York Time 4 am. As per my Calc.

    Cheers
  14. 0
    Hannes de Bruyne ·
    Hi,

    I think, the MPX is a very poor tool! The nicest way to convert is with help of RA!
    Just write a small macro in Excel to read from MS-Project and to write into P3. If you are interested I can help you with the first steps. I don’t want to send the whole macro, as I would like to see if new ideas arrise, but I’m pleased to help with basics and support in this forum.

    You will need an Excel-File with a sheet called "Activity" for this:

    Option Explicit

    Dim MSProj, ProjAppl As Object
    Dim A As Assignment

    Dim strName, TaskName, TaskSuccessor, Title As String
    Dim n As Long
    Dim bRet, Down, DoOff, FrOff, SaOff, SoOff As Boolean
    Dim iColumn, iEmpty As Integer
    Dim Cal As Calendar
    Dim Fil As Filter
    Dim myRange As Range

    ’Primavera P3
    Dim Pos1, Pos2, Pos3, Pos4 As Long
    Dim UserName, Password, ProjectName, SuccHelp, WBSstring, fname As String
    Dim iRow, i, j, l, temp, WBS(7), LastLevel As Integer
    Dim Session, P3Proj, Act, Log, Succ, Res, P3Cal, P3GloCal, ProjAbstr, ResAssign As Object
    Dim HoDay, Level, ResLimit, ACodes, CodeVal, CDI, P3Filter As Object

    Sub fromMStoP3()
    ’Call ReadMSPjroject
    Call WriteP3
    End Sub

    Function ReadMSPjroject()
    Set MSProj = CreateObject("MSProject.Project")
    Set ProjAppl = MSProj.Application

    Title = "Please Select Microsoft Project File"
    fname = Application.GetOpenFilename("Microsoft Project Files (*.mpp), *.mpp", , Title)


    ProjAppl.FileOpen fname, ReadOnly:=False, FormatID:="MSProject.MPP"
    strName = ProjAppl.ActiveProject.Name
    Application.DisplayStatusBar = True



    ’****************************** ACTIVITIES ***************************************

    Worksheets("Activity").Activate
    Cells.Select
    Selection.ClearContents
    Cells(1, 16) = "ProjStart:"
    Cells(1, 17) = ActiveProject.ProjectStart
    Cells(1, 18) = "ProjFinish:"
    Cells(1, 19) = ActiveProject.ProjectFinish
    Cells(1, 20) = "StatusDate:"
    Cells(1, 21) = ActiveProject.StatusDate
    Cells(1, 22) = "Version:"
    Cells(1, 23) = ActiveProject.VersionName
    Cells(1, 24) = "Digits:"
    Cells(1, 25) = ActiveProject.CurrencyDigits
    Cells(1, 26) = "StartWeekOn:"
    Cells(1, 27) = ActiveProject.StartWeekOn


    Cells(1, 1) = "Activity"
    Cells(1, 6) = "Headers"
    Cells(1, 11) = "Constraints"
    Cells(1, 13) = "Actual"

    Cells(2, 1) = "ID"
    Cells(2, 2) = "NAME"
    Cells(2, 3) = "OD"
    Cells(2, 4) = "Successors"
    Cells(2, 5) = "Milestone"
    Cells(2, 6) = "Summary"
    Cells(2, 7) = "Number"
    Cells(2, 8) = "Level"
    Cells(2, 9) = "PSP"
    Cells(2, 10) = "Note"
    Cells(2, 11) = "Date"
    Cells(2, 12) = "Type"
    Cells(2, 13) = "Actual Start"
    Cells(2, 14) = "Actual Finish"
    Cells(2, 15) = "Percent Compl."
    Cells(2, 16) = "Calendar"
    Cells(2, 17) = "Text1"
    Cells(2, 21) = "Resources"


    For i = 1 To ActiveProject.Tasks.Count
    Application.StatusBar = "Reading activity " & i & " of " & ActiveProject.Tasks.Count
    If Not ActiveProject.Tasks(i) Is Nothing Then

    Cells(i + 2 - iEmpty, 1) = ActiveProject.Tasks(i).ID
    Cells(i + 2 - iEmpty, 2) = ActiveProject.Tasks(i).Name
    Cells(i + 2 - iEmpty, 3) = ActiveProject.Tasks(i).Duration / (ActiveProject.HoursPerDay * 60)
    Cells(i + 2 - iEmpty, 4) = ActiveProject.Tasks(i).Successors
    Cells(i + 2 - iEmpty, 5) = ActiveProject.Tasks(i).Milestone
    Cells(i + 2 - iEmpty, 6) = ActiveProject.Tasks(i).Summary


    Cells(i + 2 - iEmpty, 10) = ActiveProject.Tasks(i).Notes
    Cells(i + 2 - iEmpty, 11) = ActiveProject.Tasks(i).ConstraintDate
    Cells(i + 2 - iEmpty, 12) = ActiveProject.Tasks(i).ConstraintType
    Cells(i + 2 - iEmpty, 13) = ActiveProject.Tasks(i).ActualStart
    Cells(i + 2 - iEmpty, 14) = ActiveProject.Tasks(i).ActualFinish
    Cells(i + 2 - iEmpty, 15) = ActiveProject.Tasks(i).PercentComplete
    Cells(i + 2 - iEmpty, 16) = ActiveProject.Tasks(i).Calendar
    Cells(i + 2 - iEmpty, 17) = ActiveProject.Tasks(i).Text1
    Cells(i + 2 - iEmpty, 18) = ActiveProject.Tasks(i).Text2


    Else
    iEmpty = iEmpty + 1
    End If
    Next i
    Exit Function

    NoFileOpen:
    ’MsgBox MSG_NOFILEOPEN, vbExclamation + R_TO_L, Title:=Application.Name
    End ’Makro beenden.

    End Function

    Function WriteP3()
    Set Session = CreateObject("P3Session")
    UserName = Application.InputBox("Please enter Username:", "P3-Login", "debruyne")
    Password = ""
    bRet = Session.Login(UserName, Password, True)
    ProjectName = Application.InputBox("Please enter ProjectName:", "P3-Project", "ms00")
    Set P3Proj = Session.Openproject(ProjectName, 0, 99)


    Application.DisplayStatusBar = True

    Application.StatusBar = "Deleting Activities..."
    For i = 1 To P3Proj.Activities.Count
    bRet = P3Proj.Activities.Remove(P3Proj.Activities.Item(P3Proj.Activities.newcursor().getfirst().ActivityID))
    Next

    Application.StatusBar = "Deleting Resources..."
    For i = 1 To P3Proj.resources.Count
    bRet = P3Proj.resources.Remove(P3Proj.resources.Item(1))
    Next

    Application.StatusBar = "Deleting Calendars..."
    For i = 1 To P3Proj.GlobalCalendar.Holidays.Count
    bRet = P3Proj.GlobalCalendar.Holidays.Remove(P3Proj.GlobalCalendar.Holidays.Item(1))
    Next i

    For i = 1 To P3Proj.Calendars.Item(1).Holidays.Count
    bRet = P3Proj.Calendars.Item(1).Holidays.Remove(P3Proj.Calendars.Item(1).Holidays.Item(1))
    Next i

    For i = 1 To P3Proj.Calendars.Count - 1
    bRet = P3Proj.Calendars.Remove(P3Proj.Calendars.Item(2))
    Next



    ’******************************** ACTIVITIES ***************************

    iRow = 3
    Worksheets("Activity").Activate

    Do While Cells(iRow, 1) <> ""

    Application.StatusBar = "Adding activity " & Cells(iRow, 1)

    Set Act = P3Proj.Activities.Newitem() ’Prepare for new activity’s data
    Act.ActivityID = CStr(Cells(iRow, 1)) ’Set ID to worksheet value
    Act.Description = Left(Cells(iRow, 2).Text, 48) ’Set Title to worksheet value
    Act.OriginalDuration = Cells(iRow, 3) ’Set OD to worksheet value
    If Cells(iRow, 5) = True Then
    Act.ActivityType = 3 ’Start Milesone
    If Cells(iRow, 12) = 6 Then Act.ActivityType = 4 ’finish Milestone
    End If
    If Cells(iRow, 6).Text = True Then Act.ActivityType = 6



    If Cells(iRow, 12) > 0 Then
    temp = Cells(iRow, 12)
    Select Case temp
    Case 1
    Act.FloatConstraintType = 9
    Case 2
    Act.MandatoryConstraintType = 5
    Act.MandatoryConstraintDate = CDate(Cells(iRow, 11))
    Case 3
    Act.MandatoryConstraintType = 6
    Act.MandatoryConstraintDate = CDate(Cells(iRow, 11))
    Case 4
    Act.EarlyConstraintType = 1
    Act.EarlyConstraintDate = CDate(Cells(iRow, 11))
    Case 6
    Act.EarlyConstraintType = 2
    Act.EarlyConstraintDate = CDate(Cells(iRow, 11))
    End Select
    End If
    If IsDate(Cells(iRow, 13)) Then Act.ActualStart = CDate(Cells(iRow, 13))

    If IsDate(Cells(iRow, 14)) Then Act.ActualFinish = CDate(Cells(iRow, 14))

    If Cells(iRow, 15) > 0 Then
    Act.PercentComplete = Cells(iRow, 15).Text ’Set AF to worksheet value
    ’act.RemainingDuration = act.OriginalDuration - act.PercentComplete * act.OriginalDuration
    End If


    bRet = P3Proj.Activities.Add(Act) ’Add the new activity info to the database



    ’*************************** ACTIVITY.LOGS ******************************

    iColumn = 10
    If Cells(iRow, iColumn).Text <> "" Then
    l = Len(Cells(iRow, iColumn).Text)
    Pos1 = 1
    i = 1

    Do While Pos1 < l + 1 And Pos1 <> 0
    Pos2 = InStr(Pos1 + 1, Cells(iRow, iColumn).Text, Chr(13))
    Set Log = Act.ActivityLogs.Newitem()
    Log.SequenceNumber = i
    If Pos2 = 0 Then
    Pos2 = l + 1
    End If
    Log.Text = Left(Mid(Cells(iRow, iColumn).Text, Pos1 + IIf(Pos1 = 1, 0, 1), Pos2 - Pos1 + IIf(Pos1 = 1, 0, -1)), 48)


    bRet = Act.ActivityLogs.Add(Log)
    i = i + 1
    Pos1 = InStr(Pos1 + 1, Cells(iRow, iColumn).Text, Chr(13))
    Loop
    End If
    Pos1 = 1
    iRow = iRow + 1
    Loop

    P3Proj.SchedulingOptions.ListConstraints = True
    P3Proj.SchedulingOptions.ListOpenEnds = True
    P3Proj.SchedulingOptions.ListOutOfSequenceProgress = True

    ’P3Proj.SchedulingOptions.UseProgressOverride = False
    Call P3Proj.ExecuteSchedule

    Session.closeproject P3Proj
    Session.logout
    End Function



    Regards
    Hannes de Bruyne
  15. 0
    Hannes de Bruyne ·
    (Ok, this is converting from MSProject to P3 - I think this is the more important direction - but it shows how to do it. I also created a macro the other way around. If you are interested let me know)

    I wonder, no reactions on my macro – it was read, but no answers. Although the idea is very good, maybe it does not work on other computers or people are not so familiar with macros as I thought they are. Maybe the whole thing needs a little more explanation:

    What you need is:

    •     P3 together with Ra – as Ra is installed with P3 this should be no question.
    •     A P3 – File, that can be overwritten (Call it something like MS00)
    •     Microsoft Project or at least the file MSPRJ.OLB in the directory c:\programms\microsoft office\office 10
    •     A MS_project file with activities, resources and everything (Call it something like Test.mpp)
    •     Excel
    •     An Excel file (Call it translate.xls). This file should have the sheets: Activity, Resource, WBS-Dictionary, Activity-Code, Filters, CDI and Calendar. (some of them are not used yet, but are for future extension)
    •     A macro. Mark the macro text from the example and copy it (CTRL+C). In the excel file go to the menu Extras -> Macro -> Macros. The Macro-name should be “fromProjectToP3”. You’r in the Visual Basic editor now and should read something like :

    Sub FromProjectToP3()
    End Sub

    This text must be marked, as it must be overwritten. Paste the text you have copied (see 8 lines before). (CTRL+P). Take care, it has overwritten the 2 lines. Now you have a macro, but it does not work yet. The file MSPRJ.OLB, which is the MS-Project equivalent to Ra is still missing. As you are still in the Visual Basic editor go to the Menu Extras -> Reference (I think this line is called reference, but as I use a German version I’m not quit sure – at least it is the first line). Now search for “Microsoft Project 10.0 Object Library” and mark this line. Now the whole thing should work. Leave Microsoft Visual Basic by clicking the Excel Icon (Top Left in the menu-line of this window) .
    You can start the macro now Extras->Macro->Macros->fromMStoP3->run (or is it execute?).
    Select a MSProject-File and you will see it fills the Excel-sheet. The second part asks far username and –file for P3 and writes into P3.

    One small error is in the macro ’Call ReadMSPjroject should NOT have this mark before Call. I used it for testing.

    The part with the links is not yet in the macro, it will come next week.



    I could have written this macro in MS-Visual Basic, make an *.exe file out of it and sell it, but I don’t like the Idea. I rather make it an open-source code, and add the improvements, reaction and proposals to it. So do ask questions, write me if errors occur,

    Furthermore I think Ra with Excel-Macros can solve a lot of other problems with Primavera e.g. P3 is not restricted to just one WBS-Code-Structure. Or you can link P3 and AutoCad! Many of the questions I read in this forum can be so easily solved with small macros. A forum is not just for questions and answers it also needs new ideas.

    I hope this is a first step for many people in the macro- world



    Hannes de Bruyne
  16. 0
    X Planner ·
    Hannes,
    thank u very much for ur help,
    i tried another way and it kinda worked with me
    i used the preimavera enterprise v3.5 to convert, and it was done.

    sorry, i’m not as good as u working with the macros ,so i had no comment.

    thanks again

    REGARDS,

  17. 0
    Jose Frade ·
    Hannes,

    Thanks for the idea.
    Obviously it needs some knowledge about macros.

    What is good in it is the opening of the complete field you showed.

    Best regards
    Wadgassen - Germany.

    JMFrade
  18. 0
    Sean Magee ·
    Be very careful when transfering data from P3 to MSP and Vica Versa the MSP does not handle this tranfer very well.
    You query focuses on how codes tranfers when equally important is the fact that calendar related data does not transfer accurately.
    Any activity with a lag on will use the standard (project calendar) in MSP to reschedule your data.
    This may be O.K if your original P3 project has a five day calendar as standard however if you have multiple calendars in P3 say a mix of five day working calendars and 7 day working then MSP will default to using the five day calendar to calculate lags. MSP is not able to handle the transfer too well. The best thing is to leave things as they are as P3 is a far superior planning package.
    But if you feel you must go down this route then look further than coding as other data may not be the same.
  19. 0
    Hannes de Bruyne ·
    Hello Sean,

    MSP and P3 actualy work with the same system, both can have calendars and have a main calendar. In my complete programm, I also developed a system to transfer these calenders and the calendar-ID.
    The reason why I did not build in this transfer yet, is that I hoped to get some new ideas in this forum.

    Hannes de Bruyne
  20. 0
    Gün Göksu ·
    I understand from this tread that Ra is basically used to enable macros (excel for example) to directly modify P3 data tables. is this true?

    something like an API???

    thus Activity.xls is using this Ra?
    (looks like I need to reread the manuals).

    but It seems obvious to me that there is a lot more to it than found in the manuals (in the CD). people keep poping up with new code like from nowhere.

    What is the background of research to accumulate to spurt this kind of stuff?

    Gün.
  21. 0
    Hannes de Bruyne ·
    Right !

    A lot of Software have ActiveX-elements, which are the basics for those makros. Sometimes they are even hidden or at least don’t have any documentation.
    With these ActiveX-elements you can link almost everything, either with Visual Basic to create *.exe files or with Visual Basic for Applications, which is inside MS-Programms.
    Using Excel is the most easiest way, as you can store and manipulate data. System like these (DDE, OLE etc.) are available in operating systems since DOS but only used by a small group of users. Most people think its difficult to use, but as soon as you have started, you find it quit easy and find new things every day. You find a lot of support in the internet.

    Here is a very simple makro for P3. You need an Excel-File with the sheets "P3-Resources" and "Success". Start Extras->Macros->Visual Basic Editor and copy this text inside. Now you have a macro called Primavera. It opens a P3-file and writes a few Data into Excel. For the rest also see the Ra.hlp - file.

    Dim session As Object
    Dim proj As Object
    Dim act As Object
    Dim res_id As Object
    Dim succes As Object
    Dim bret As Boolean
    Dim username, password, projectname As String
    Dim xRow, ActNos As Integer
    Dim sheet As Workbooks

    Sub Primavera()
    Set session = CreateObject("P3Session")
    username = Application.InputBox("Please enter Username:", "login", "debruyne")
    password = ""
    bret = session.Login(username, password, True)

    Worksheets("P3-Resources").Cells(1, 1).Value = "ActivityID"
    Worksheets("P3-Resources").Cells(1, 2).Value = "Description"
    Worksheets("P3-Resources").Cells(1, 3).Value = "Resource"
    Worksheets("P3-Resources").Cells(1, 4).Value = "BudgetedCost"
    Worksheets("P3-Resources").Cells(1, 5).Value = "BudgetedQuantity"
    projectname = Application.InputBox("Please enter ProjectName:", "project", "li01")
    Set proj = session.openproject(projectname, 0, 99)
    xRow = 2
    ActNos = 1
    For Each act In proj.activities
    Worksheets("P3-Resources").Cells(xRow, 1).Value = act.ActivityID
    Worksheets("P3-Resources").Cells(xRow, 2).Value = act.Description
    For Each res_id In act.ResourceAssignments
    Worksheets("P3-Resources").Cells(xRow, 3).Value = res_id.ResourceName
    Worksheets("P3-Resources").Cells(xRow, 4).Value = res_id.BudgetedCost
    Worksheets("P3-Resources").Cells(xRow, 5).Value = res_id.BudgetedQuantity
    xRow = xRow + 1
    Next
    ActNos = nos + 1
    Application.StatusBar = ("Activity: " & xRow)
    Next


    Worksheets("Success").Cells(1, 1).Value = "ActivityID"
    Worksheets("Success").Cells(1, 2).Value = "Description"
    Worksheets("Success").Cells(1, 3).Value = "Driving"
    Worksheets("Success").Cells(1, 4).Value = "Successor"
    Worksheets("Success").Cells(1, 5).Value = "Lag"
    Worksheets("Success").Cells(1, 6).Value = "Type"
    xRow = 2
    ActNos = 1
    For Each act In proj.activities
    Worksheets("Success").Cells(xRow, 1).Value = act.ActivityID
    Worksheets("Success").Cells(xRow, 2).Value = act.Description


    For Each succes In act.Successors
    Worksheets("Success").Cells(xRow, 3).Value = succes.IsDriving
               Worksheets("Success").Cells(xRow, 4).Value = succes.SuccessorActivityId
    Worksheets("Success").Cells(xRow, 5).Value = succes.RelationShipLag
    Worksheets("Success").Cells(xRow, 6).Value = succes.RelationShipType

    xRow = xRow + 1
    Next
    ActNos = nos + 1
    Application.StatusBar = ("Activity: " & xRow)
    Next

    session.closeproject proj
    End Sub



    Hannes de Bruyne

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?