Getting overall progress in P3
In the Open Standard
Frank DuncanMember for 20 years 11 months
- Created
- 3
- 1
0
Hi, I have some questions for the experienced P3 users.
First, I wish to know about the % COMP field (PERCENT COMPLETE) on a resource-loaded schedule for a construction project. The % COMP is based on what?
- Quantities installed?
- Duration consumed?
Second, knowing that this % COMP field is valid only for each activity, how do you get the overall progress? I wish to get the S-curve graph with the planned and actual lines, but how do you get it if the activities have different unit of measures (i.e. LM, M3, EA, and so on)? If you use a unified unit of measure, what report do you use and what data do you export to elaborate the graph using thrid party software, such as Excel (they told me P3 is bad elaborating graphics)?
Thank you very much.
First, I wish to know about the % COMP field (PERCENT COMPLETE) on a resource-loaded schedule for a construction project. The % COMP is based on what?
- Quantities installed?
- Duration consumed?
Second, knowing that this % COMP field is valid only for each activity, how do you get the overall progress? I wish to get the S-curve graph with the planned and actual lines, but how do you get it if the activities have different unit of measures (i.e. LM, M3, EA, and so on)? If you use a unified unit of measure, what report do you use and what data do you export to elaborate the graph using thrid party software, such as Excel (they told me P3 is bad elaborating graphics)?
Thank you very much.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?