Skip to content

P3 files

A DMember for 19 years 5 months
Created
13
4
0
Hi Guys,

can I have a list of P3 files (23 files). Like for a program say ABCD.p3, ABCDREL is the file containing all activity relationships. Can I have description for all those 23 files?

(What i am looking as of now is ACTUAL DATE file)

:-)

Ravi

13 replies

Oldest first
  1. 0
    Steven Oliver ·
    The files are only readable when opened with P3 anyway. So knowing which file relates to which data table doesnt really get you anywhere
  2. 0
    A D ·
    dear Steve,

    I need it to replace the actual date file.

    Now, suppose, if i have to delate all relationship in the project, I create a blank project and then rename it and then replace it with the old project. This will delete all the relationships in the project.

    Now, in my present case, I want to import all the actual dates from program say, ABCD to Target program, say EFGH. If i rename the ABCD (actual date) file, and then paste it in the EFGH folder, then all the actual dates will be replaced. this is what I want to do. I can do it by Import/export as well, but I hav now Excel 2007 installed which doesn’t support WK1 extension.

    Am I clear?

    So, I need the description of the files. Urgent Plz.

    Cheers,

    Ravi
  3. 0
    Ferdinand U. ·
    i have asked the same see this posting


    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=41758
  4. 0
    Ferdinand U. ·
    ????.ACT contains actual as far as i know, but please check

    and tell us also
  5. 0
    A D ·
    ACT contains activity description.

    ??????

  6. 0
    A D ·
    Thanks Ferdi for the post, but it seems there is no as such specific file for actual dates.

    Thanks anyway.

    Cheers,

    Ravi
  7. 0
    Ronald Winter ·
    You do not need to delete the data to return a completed schedule to the un-started baseline schedule. Instead, use Global Change to make these changes

    For every activity, set:
    Actual Start = " "
    Actual Finish = " "
    Remaining Duration = Original Duration
    Percent Complete = 0

    Good luck!
  8. 0
    Sajid Balma ·
    Hi
    You can download very powerful xls macros from the following link
    ftp://suppsaleserver.primavera.com/utils/EXCEL/
    Using these excel files you can GET data and SET data in any of p3 files. I hope this will serve the purpose.
    Regards
  9. 0
    A D ·
    Thanks Ronald for the tip, but I dont know weather I have explanied it correctly or not!!

    Lets try it again!!!

    I have a updated program say, ABCD with 1900 activities. Now I want to have all those actual dates into the master baseline program, say EFGH having 22000 activities. In baseline program, activities of ABCD are linked with other different phases.

    I just thought there must be some way to just change the actual dates. Is there any?

    ???

    Ravi
  10. 0
    A D ·
    Thanks Sajid,

    Those tools were bit useful, if u need to export teh stuff from P3 to excel. But, then do u hav any tool to import the data back (apart from Import / export).

    Cheers,

    Ravi
  11. 0
    Gerry Ampo ·
    Hi,

    Maybe,..You can use the options of the UPDATE TARGET dialog box to automatically update the Actual dates of your target project.

    To do this, you can go to Tools, Project Utilities, Target. Click the Update botton. On the dialog box, check "All Activities", "Underway" & "Completed".

    Then on Store, check "Actual Dates". See to it that the other check boxes are cleared. Click UPDATE.

    To do this, you need to have "exclus1ve access" to both baseline and current project.

    Just try to have a back-up copy of your Baseline project, just in case..

    Best regards
  12. 0
    A D ·
    Thanks Gerry,

    Thanx a ton
  13. 0
    Sajid Balma ·
    Hi Ravi

    Although u have already got better tip from Gerry but just to let you know that those excel macros work a bit differently. If you go to Tool-Macros (in Excel), you will see a long list of macros having names like GetActivity....Set Activity....
    There you can retrieve (by using Get....) any data from any p3 files and then write your data in any p3 file using Set.... macros.

    Cheers

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?