in order to update the project we always need % complete of that purticular activity

how this % complete is being measured??

as the best practice we normally use PMS

can any guy send me some samples of Physical Progress Measurement System for heavy contruction/Roads/Dam projects

thanks

engriqbal@yahoo.com

6 replies

Oldest first
  1. 0
    Neeraj Agarkar ·
    This would easily fill a book.
    pretty basic thing is to go by your Bill of Quantities. or identigy the total scope of work from drawings and measure actual against that. basic as i said.
  2. 0
    Muhammad Iqbal ·
    Hi

    Neeraj

    My dear sir

    in BOQ there are only pay item but while executing some task there are some of activities that normally are not present in BOQ for this we need PMS

    Example

    "Lay of Grade Beam Concrete"

    in BOQ only available Item is "concrete"

    before the concrete there are

    activity like

    Layout marking.

    Fabrication of Formwork

    Fabrication of Steel bar/Rebars

    Epoxy coating to Rebars

    Fixing of Rebars
    Installation of Forms
    and then Pouring of Concrete(can be found in BOQ)

    Removal of Forms
    Sparying of Curing Compound

    so how you will monitor other activities

    this is one example

    but if go for big project like

    Barrage ,Dam. Air Port or some High way ,Cross Country Pipe line You should have to develop PMS for monitoring

    i hope u got my point

    if any body can have i will appreciate

    have fun


  3. 0
    Charleston-Joseph Orbe ·
    Hello,

    That is really a problem because you need to have the estimated quantities per items in your activities while the BOQ quantities are build-up.

    There is no short cut. You have to do it the engineering way or you can drag the quantity surveyor and let him do the quantity take off since that is his job.

    Also in updating progress, you need to get the cooperation of project QS to get the actual quantity in place.

    Cheers,

    Charlie
  4. 0
    Neeraj Agarkar ·
    Hi Muhamad,
    You are partially right. Some industrial projects have very less value of Civil works compared to overall project value. In such cases BOQ is not detailed down to formwork, rebar and concrete.

    But quantities are always available. How else did you quote for the project? In any case, you have "Good for construction" drawings which should be used for QTO. This is QS job as charles said.

    As a last resort, if you really don’t get quantities in time, but still want to measure Progress, you can set weightage points. This is purely based on experience.
    I do it for progressing Procurement activities.



  5. 0
    Muhammad Iqbal ·
    Hi

    M/s

    Neeraj & Charlie

    I do respect your responses and ideas

    your approach is great when you are working on small to medium value project where you are only Schedule controlling.

    i was concern in EVM

    where cost and time are to be controled so for such projects we are sure need a formal PMS Documents and it also depends how big is the organization.

    I was only intrested if any body is working on PMS he may please send me the PMS

    %WT is not great idea for Heavy Construction work like Dams ,Barrges

    thanks






  6. 0
    David Benjamin ·

    hiWhat is the full form of

    hi

    What is the full form of PMS, what is this. Who is having this. I am also eager in this matter.

    sd_benjamin@yahoo.com

    sdbenjamin@gmail.com

    david.benjamin@wjtowell.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?