About leveling o resources with P3

Sara BankesMember for 20 years 11 months
Created
3
1
0
When do you do leveling of resources (using a tool such as P3, or other) ... during the planning phase or execution phase (or both)? ... I appreciate your opinions and answers on this issue. Thanks.

3 replies

Oldest first
  1. 0
    Ganesan Sebrenmani ·
    Resource leveling is needed both at earlier stage of planning and during progress updating.

    it is needed when the schedule is resource driven rather than time driven.

    when your resources are limited, levelling helps you to organize activities according to logic sequences and resources availablity or limits.
  2. 0
    Sara Bankes ·
    Thanks for your answer ... so you mean you only level the resources when the schedule is resource-driven??? are you sure?
  3. 0
    Ganesan Sebrenmani ·
    Resource levelling also needed for time-driven schedules.
    for example :

    when you level a time driven schedule with limited resource, P3 will show areas where the resource needed, is over the maximum limit of what is available.

    From there you decide to use more resource for that particular time or extend your duration for that activity or the whole project.

Log in or join to reply