How P3 is handling relationships?
In the Open Standard
MM
Mohd MahdMember for 25 years 3 months
- Created
- 16
- 4
0
Hi,
Any better idea of the subject question!
let’s make an ex.
if two activies A & B of 10 and 15 days. B should start after 4 days of A start.
What is better to logic them?
Should they B SS A with 4 days +ve lag. OR
B FS A with 6 days -ve lag.
Take P3 only into consideration. i.e. the nature of the activities allow using both logic.
Any better idea of the subject question!
let’s make an ex.
if two activies A & B of 10 and 15 days. B should start after 4 days of A start.
What is better to logic them?
Should they B SS A with 4 days +ve lag. OR
B FS A with 6 days -ve lag.
Take P3 only into consideration. i.e. the nature of the activities allow using both logic.
16 replies
Oldest first- 0SOSteven Oliver ·Surely, it depends on the relationship between the two activities.
If the start of B is dependant upon the progress made on A, then the only credible (IMHO) relationship would be FS with negative lag, as the SS relationship effectively says that 4 days after A has started, B can start, independent of the progress made on A.
- 0RIRashid Iqbal ·Hi All,
If and only if the start of B is dependent upon the start of A then B having A as a predecessor with SS+4days is good enough. Though if B is also dependent upon the producivity/speed/buffer of A then it should be FS or even FF.
To clarify as from where i am comming from,i’ll explain as follows.
When i am saying B is dependent upon the progress/buffer of A, I consider A being the ’Subgrade’ and B being the ’Spreading of Gravel’ in a project of highway construction. B could start after 4 days as there would be enough (buffer) subgrade available though after a few days if the A slows down then B has to automatically match with the speed of A and in this case FF or FS with ’Retained Logic’ would model the situation realistically.
Regards
Rashid Iqbal
- 0PHPaul Harris ·Microsoft Project allows a SS+50% or a FS-50% relationship.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
- 0HDHannes de Bruyne ·I think the most important thing is the length of the first activity. If the first activity has a length of 365 days and something has to happen somewhere at the end, the best solution is a negative lag. Because, if something happens on the way of the first activity a SS relationship can never show the influence on the second activity. So you have to consider case by case. Important is to describe the relationship by your own words - the best description mostly is the best link.
Hannes - 0MSMarcio Sampaio ·Sorry ... but sometimes i think that we complicate simple things.
The question was:
"if two activies A & B of 10 and 15 days. B should start after 4 days of A start.
What is better to logic them?
Should they B SS A with 4 days +ve lag. OR
B FS A with 6 days -ve lag."
MAKE IT SIMPLE - That is the best answer.
- 0MMMohd Mahd ·thanks deeply for everybody answer
however, my question is after something else.
in fact, it will be very debatable, if we consider the nature of the activity. in this case, every activity has its own answer, ex engg activities will different from construction and from IT ones...... etc.
i am looking specifically for how P3 is handling it. and what is better for P3? or they r equal? specially when progressing....
with my great appreciate for each word of yours. - 0PHPaul Harris ·Just type in +50% etc in the lag box in the same way as one would type in a lead or lag of say +5d or -5d.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
- 0MMMohd Mahd ·MSP ???? i think this is about P3
let me rewrite my question
.
.
thanks deeply for everybody answer
however, my question is after something else.
in fact, it will be very debatable, if we consider the nature of the activity. in this case, every activity has its own answer, ex engg activities will different from construction and from IT ones...... etc.
i am looking specifically for how P3 is handling it. and what is better for P3? or they r equal? specially when progressing....
with my great appreciate for each word of yours. - 0CAChristian Adrian De Vera ·Hello Paul
Admittingly, I haven’t tried that kind of logic yet(FS-50%) but as I used it in my sample project I noticed that it is same as using days as lag too... would there be a significant implication in terms of progress updating (compared to the usual way of using days as lag)..?? as I know there’s none in P3 like this...
Kind regards,
Christian
Log in or join to reply