Deleting Relationships in P3.1

Santhosh kumarMember for 18 years
Created
21
4
0
In P3.1, is it possible to delete at a time all the relationships in a project?(Not by deleting the relationships individually)"Unlink" option doesn’t serve this purpose it seems.

21 replies

Oldest first
  1. 0
    Shah. HB ·
    HI

    I guess you can export and delete all the links and then import using activity ID
  2. 0
    Santhosh kumar ·
    Hi,

    Even if we delete the links and then import, still the link remains.
  3. 0
    Shaneouz Kallal ·
    Hi,
    To unlink all relationships – First go windows folder and open P3.INI file then add the following line to the [Options]:
    UnlinkAllRels=1

    To unlink only finish to start relationships, change the line to UnlinkAllRels=0.

    Save and exit the file.

    Now select all activities and mark Unlink option. Hope it will work
  4. 0
    Santhosh kumar ·
    Hi Shaneouz,

    Thanks for the reply
    But I could not find P3.INI file in the Windows folder?
  5. 0
    Anbin Ponnith ·
    Hai Santhosh
    In my System I found it in C:\Windows\P3
    It is a Notepad File
    R U can Find it Using Search Option
    Follow the rest of thing as Shaneouz told,I Tried it & It works for me
    Thanks Mr.Shaneouz

    Regards
    Anbin Ponnith
  6. 0
    Ferdinand U. ·
    It has been answered long time ago

    here’s the link:

    http://www.planningplanet.com/forum/forum_post.asp?Cat=2&Top=12799
  7. 0
    Santhosh kumar ·
    Thanks Anbin & Shaneouz

    I got it.


  8. 0
    Atif Ali ·
    Thanks Anbin & i tried that method & it really work
  9. 0
    Santhosh kumar ·
    Another hurdle on the way!
    I have Civil,Mechanical,Electrical,Commissioning activites in my schedule.
    All these are inter and intra linked.Now i want to delete the inter links and the intra links of electrical activities only and maintain the other inter & intra links of other activities.

    Is it possible?
  10. 0
    Shah. HB ·
    Thanks shaneouz ,perfect solution
  11. 0
    A D ·
    There’s one more way out...

    There r 23 files with each program.

    One of the file is rel.p3

    replace the current project rel.p3 file with a blank rel.p3 and all ur relationships will be deleted.

    Cheers,
  12. 0
    Shah. HB ·
    @ Raviraj

    Replacing blank rel.p3 should be from the newly created project file or the same project file without links ?
  13. 0
    A D ·
    from the newly created project file. REL file stores only the relationships

    u can try with one of ur draft programs.

    IT WORKS
  14. 0
    Shah. HB ·
    Many thanks Raviraj,
  15. 0
    Rafael Davila ·
    Raviraj,

    What happens to the hammock activities? No issue at all? Does P3 warns you of undefined links for hammock activities or not?

    SureTrak being a lower end product does not warns you about undefined links in hammock activities while other high end software warns you about hammock activities with undefined links.

    Out of curiosity I no longer have P3 and SureTrak will be gone from my computer in a few weeks after my last SureTrak job is finished.

    Best regards,
    Rafael
  16. 0
    Shah. HB ·
    hi

    on doing below mentioned procedure hammock also remain unlinked
  17. 0
    A D ·
    Thanks Shahul for answering that. The REL file contains all the relationships including hammock.
  18. 0
    Osama Warid ·
    Dear anbin
    The change on file p3.INI will not change the configration of the soft ware it self?
  19. 0
    Rafael Davila ·
    Thanks to all.

    It worked with SureTrak P3 files,same as if P3 the hammocks links were erased.

    Good to know in case I ever have to use SureTrak again.

    Best regards,
    Rafael
  20. 0
    Mike Testro ·
    Hi All

    I have been following this thread with a wry interest.

    To delete links in powerproject you just click on the link - it turns green - and hit delete on the key board.

    To delete all links just click on one link - select all - and all links go green - hit delete.

    If you want to retain links in a hammock then lable the links as "hammock" and deselect this category before deleting.

    Why can’t all software be that simple.

    Best regards

    Mike Testro.
  21. 0
    Rafael Davila ·
    Mike,

    P3 and SureTrak are outdated software, not supported by Primavera anymore. New software has better functionality as it is the case for Asta Power Project. The solution supplied here for P3 is the best I heard up to now for this particular software.

    In Spider Project you delete them using the links table view; after sorting, filtering, selecting all or selecting individually a few ones. Only selecting one or all without the option to select from a filter, sort or a selection where you cannot clearly see the link definition is somewhat limited, don’t use the Gantt view, is confusing and error prone.

    Delete Links

    Best regards,
    Rafael

Log in or join to reply